Page 570 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 570

The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices  Best Practice 1 0.7
              Maintaining a flushing log is important to ensure that all  Final inspection and start-up checks
              flushing procedure requirements are carried out. In addition,
              periodic inspection of flushing screens is suggested to ensure  The contractor and the customer must mutually agree on an
              the job is proceeding smoothly. It is a common occurrence that  acceptable hand over and sign off procedure. As a minimum the
              the length of a flushing cycle frequently exceeds its predicted  following items should be completed:
              time. The procedure provided in the appendix and the guide-
              lines presented in this section will ensure that flushing will be  - All installation and long term storage requirements
              accomplished in the minimum amount of time. However ef-  - All auxiliary piping, installation, insulation and painting
              fective a procedure is, it is only as effective as its imple-  - All instrument and electrical loop checks complete and
              mentation. Therefore, monitoring the flushing operation is  proven operable
              imperative.                                          - All spare parts received and equipment documentation
                Figure 10.7.2 presents additional considerations regarding  available
              flushing.
                One final word regarding flushing: it has come to our at-  First start, run-in and initial operation
              tention that in an effort to ensure totally clean systems, too
              many flushing screens are employed, resulting in excessive
              flushing times. A common example of this practice is the  After the equipment has been handed over, first start, run-in and
                                                                   initial operation should be performed in accordance with proven
              installation of flushing screens in drain lines. Since drain lines
              are designed to operate only half full, a flushing screen will  start-up procedures and planned operation procedures.
                                                                   Figure 10.7.3 provides these considerations.
              eventually become partially plugged. When it does, the level
                                                                     Included at the end of this section are the following addi-
              of the oil in the affected drain line will rise and will very  tional documents that contain valuable guidelines for site pre-
              effectively clean the top of the pipe. Since this is an abnor-
              mal occurrence, and since one function of the reservoir is to  commissioning and commissioning:
              contain the sludge and prevent it from re-entering the  - Site pre-commissioning best practice list for your use
              system, excessive use of screens in drain lines should be  - Functional lube/seal system test procedure outline
              discouraged.                                         - Electro-hydraulic governor functional test procedure outline
                A practical recommendation would be to install one screen  - Steam turbine solo run functional test procedure outline
              in the main return to the reservoir for only the initial phases of
              flushing. A convenient way to ensure that this screen is not
              becoming plugged is to connect a temporary piece of plastic  Auxiliary system flushing procedure
              tubing to the bottom of the drain line close to the flushing
              screen and monitor the level of the oil. When the level begins  This information is provided courtesy of M.E. Crane, Consultant.
              to rise in the plastic tube, shut down and clean the screen  The following procedure is presented as a guide for field
              before the level becomes excessive. Once the debris on the  flushing of lube and seal systems. In order to be fully productive,
              screen has leveled out, it is suggested that the screen be  it is recommended that all requirements noted herein be strictly
              removed.                                             followed.

                                                                   1. General
                                                                     1.1 Flushing operation will be carried out by the designated
                                                                         party (contractor or owner).
                                                                     1.2 Cleanliness of oil console, equipment skid, overhead
                                                                         seal oil tanks, piping systems and screens shall be
                                                                         determined by mutual agreement between equipment
                                                                         vendor, contractor and owner.
                                                                     1.3 Owner and vendor shall keep a log for general review of
                                                                         flushing progress. Master flow sheets shall be kept by
                                                                         owner and updated to progress. An entry shall be made
                                                                         during each shift.




                                                                     1. Final inspection and hand-over accepted (all work complete,
                                                                       all punch list items complete, loop checks complete)
                                                                     2. Start-up procedure (optional) approved
                                                                     3. Air run (compressors) optional
                                                                         Procedure
                                                                         Safety considerations
                                                                         Limits of operations
              Fig 10.7.2   Cleaning of equipment and associated piping e flushing
              of lube and seal oil systems (cont.)                 Fig 10.7.3   First start, run-in and initial operation

                                                                                                               541
   565   566   567   568   569   570   571   572   573   574   575