Page 1009 - Industrial Power Engineering and Applications Handbook
P. 1009

321954 Industrial Power Engineering and Applications Handbook
             welded joints will be subjected to dye penetration   a UAT through the main bus section between the generator
             examination  and  10% of  butt-welded  joints,   and  the  generator  transformer  which  are  under  the
             including joints  on  flexibles,  enclosures  and   cumulative influence of two separate power sources, must
             conductors, will be subjected to radiographic (X-   be subjected to a higher withstand voltage as prescribed
             ray) examination.                        by  IS  8084 and indicated in column 4, Table 32.1(A).

       32.2.3  Seismic disturbances                   32.3.3 Impulse voltage withstand test (for system
        In Section 14.6 we have provided a brief account of such   voltages 2.4 kV and above)
        disturbances  as  well  as  the  recommended  tests  and   The procedure for testing will be the same as that discussed
        procedures to verify the suitability of critical enclosures   for switchgear assemblies in Section 14.3.4. The impulse
        and  bus  systems  for  locations  that  are  earthquake-   test voltage  is applied  as in Table 32.1(A) for series I
        prone.  For  this  the  user  is  required  to  provide  the   and Table 32.2, for series I1 voltage systems with a full
        manufacturer with the intensity of seismic effects at site   wave standard lightning impulse of  1.2J50 (Section 17.6.1).
        of the installation in the form of response spectra (RS).   There  should  be  no disruptive  discharge  or insulation
        (See Section  14.6.)                          breakdown.

        32.2.4  Field tests
                                                      32.3.4  Verification of temperature rise limits (or
        These are to be conducted aftcr the installation and before   rated continuous current capacity)
        energizing the bus assembly at site:
                                                      (Recommended  for  systems having a current rating of
                                                      more than 400 A)
          Checking for any human error                  This will be carried  out under  similar parameters of
          Visual inspection of the bus assembly       room  condition  and  the  type  of  test  voltage  wave  to
          Inspection of electrical wiring if there is any (such as   those  for  a switchgear assembly  (Section  14.3.5). The
          for space heaters, cold or hot air blowing or enclosure-   current in each phase should be within 2% of the specified
          pressurizing or any other protective circuit)   test value (rated current).
          Verification of insulation resistance or measurement   For LT bus systems: The length of the test piece will
          of  the  leakage  current,  both  before  and  after  the   be a minimum 6 m as in IEC 60439-2 with at least one
          dielectric HV test, if the HV test is to be carried out.   joint.  The joints  must be  both  in the conductor  and in
          Verification of dielectric properties - limited to power   the enclosure in each phase. If the total length of the bus
          frequency voltage withstand or HV test (usually not   section  is  less than  specified,  the  entire length  of  the
          recommended)                                bus  system  in  the  fully  assembled  form  will  then  be
          Watertightness and air leakage test for isolated phase   tested.
          bus systems.
                                                        For HT bus systems: The entire length of the bus system
                                                      manufactured  for a  particular  installation  in  the  fully
        32.3  Procedure for type tests                assembled  form  will  be  tested.  Each  end  of  the  bus
                                                      enclosure will be  properly sealed to eliminate any heat
                                                      leakage.
        Below we briefly outline the procedure for conducting   The bus sample is located 600 mm above floor level.
        type tests at the manufacturer's  works.      The ambient temperature  should be within  10-40"C  as
                                                      measured by  the average value of  at least four thermo-
        32.3.1 Verification of insulation resistance or   meters, two placed on each side of the enclosure on the
              measurement of the leakage current      centre line, at least 300 mm from it, and 600 mm from
                                                      the ends. The bus sample must be a three-phase unit as
        The procedure and test requirements will remain the same   well  as the test equipment  for a three-phase  system to
        as that discussed  in  Section  14.3.2, for metal-enclosed   account for the proximity effect. This effect  will  not be
        switchgear and controlgear assemblies.        reflected  if  a three-phase  system is tested  on  a single-
                                                      phase one. Similarly, a single-phase unit and single-phase
        32.3.2  Verification of dielectric properties   test equipment should be used for a single-phase system
                                                       (such as from the neutral side of the generator up to the
        Power frequency voltage  withstand or HV test   neutral grounding transformer). The test will be conducted
                                                       at the rated current until a near-stable condition is reached
        The procedure  will  be  the  same  as that  discussed  for   and three successive readings at not less than one-hour
        switchgear assemblies (Section 14.3.3). The test voltage   intervals for an LT  system  and  30 minutes  for  an  HT
        may be applied for one minute as shown in Tables 32.1 (A)   system do not  show a maximum variation of more than
        or (B) for series I  and Table 32.2 for  series I1  voltage   1°C. To  shorten the test, the current  may be increased
        systems. Any disruptive discharge or insulation breakdown   during the initial period. The test may be conducted at a
        during the application of high voltage will be considered   reduced  voltage,  as the emphasis is on heating  due to
        to be dielectric failure.                      current. For a successful test, the hottest spot temperature
          The tap-offs in a power-generating station connecting   should not  exceed the values in Table 32.3.
   1004   1005   1006   1007   1008   1009   1010   1011   1012   1013   1014