Masonry Construction Techniques
            148  CHAPTER FIVE



            QUICK>>>TIP                                (IRA) or high suction. High-suction bricks
                               To test a brick for     should be wetted with a garden hose a day
              excessive absorption, draw a circle the  or so before they will be used so that mois-
              size of a quarter on the bed surface using  ture is fully absorbed into the units but the
              a crayon or wax pencil. With a medicine
                                                       surfaces are dry to the touch before being
              dropper, place twelve drops of water
                                                       laid. Some experts recommend that brick
              inside the circle and time how long it
                                                       not be wetted in winter because some
              takes to be absorbed (Figure 5-11). If
                                                       high-suction units produce better bond
              the water is completely absorbed in less
                                                       strength in cold weather than low-suction
              than one minute, the brick is too dry.
                                                       units. Even though it is very absorptive,
                                                       concrete block should never be wetted
                                                       before placement     because this will
                                                       increase unit shrinkage and the possibility
                                          CRAYON OR
               EYE                        WAX PENCIL   of cracking in the finished wall. For this
               DROPPER                    CIRCLE THE   reason, it is particularly important to keep
                                          SIZE OF A    concrete block covered and protected at
                                          QUARTER
                                                       the job site. All masonry units should be
                                                       clean and free of contaminants such as
                                                       dirt, oil, or sand that might interfere with
                                                       mortar bond.

                                                       5.2.5 Reinforcement, Connectors,
                                                       and Accessories
                                                       Reinforcement and accessories should be
              FIGURE 5-11
                                                       checked for correct size and configuration
            Field test of brick absorption.            and for adequate quantities to complete
                                                       the work. Before placing reinforcing steel
                            or metal accessories in the wall, oil, dirt, ice, and other contaminants
                            should be removed so that a good bond can be achieved with the mor-
                            tar or grout.


                            5.3     Mixing Mortar

                            Mortar is the cementitious material that bonds units, connectors, and
                            reinforcement together for strength and weather resistance. Although
                            it contributes to the compressive strength of the masonry, mortar’s pri-
                            mary functions are in providing bond strength and in sealing the joints
                            between units against the passage of air and water. To perform these



                   Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
                              Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
                               Any use is subject to the Terms of Use as given at the website.
   144   145   146   147   148   149   150   151   152   153   154