Footings, Foundation Walls, Basements, and Slabs
            248   CHAPTER SIX



                               In areas where radon gas from the soil is a potential problem, most
                            building codes require that basements, crawl spaces, and slabs-on-
                            grade be designed to resist radon entry and that the building be pre-
                            pared for post-construction radon mitigation, if necessary. Figure 6-51
                            shows CABO requirements for basement construction. Similar details
                            apply to crawl space and slab-on-grade foundations. One of the pri-
                            mary considerations is sealing the walls and slab to prevent gas entry.
                            Dampproofing, perimeter caulk, and a below-grade air barrier are
                            important elements. A 6-mil polyethylene sheet or a 3-mil cross-lami-
                            nated reinforced polyethylene sheet is acceptable for this use. The top
                            course of hollow concrete masonry foundation walls must be grouted
                            solid to prevent air leakage to the interior space above, and a 4-in.
                            layer of gravel below the slab acts as a gas-permeable layer which can
                            be mechanically vented if needed. All control joints, construction
                            joints, and isolation joints in concrete and masonry must be caulked.











































                   Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
                              Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
                               Any use is subject to the Terms of Use as given at the website.
   244   245   246   247   248   249   250   251   252   253   254