Masonry Veneer

             276   CHAPTER SEVEN



                                                        wick is clipped flush with the wall. Mois-
                                                        ture in the cavity is absorbed by the cotton
                                                        material and “wicked” to the outside face
                                                        of the wall, where it evaporates. The rope
                                                        will eventually rot, but it leaves an open
                                                        hole for continued drainage. The rope
                                                        must be cotton rather than nylon to be
                                                        effective.
                                                           Through-wall masonry flashing must
                                                        be installed at lintels above door and
                                                        window openings, at window sills and
                                                        ledges, and at the base of the wall. Weep-
                                                        holes must be installed in the first
                                                        masonry course immediately above the
                                                        flashing. The wall sections in Figure 7-27
                                                        illustrate basic requirements of the CABO
                                                        One and Two Family Dwelling Code.
                                                        Brick masonry sills should be sloped to
                                                        drain water away from the window. The
                                                        masonry industry recommends a mini-
                                                        mum slope of 15 degrees. The flashing
              FIGURE 7-28
                                                        system must form a complete barrier to
             Expansion joint at change in wall height.  the passage of water. Masonry veneer
                                                        should always rest on a ledge recessed
                                                        below the finish floor line so that the
                              flashing at the bottom of the drainage cavity collects and discharges
                              moisture at this less-vulnerable location.


                              7.6    Expansion and Control Joints

                              As discussed in Chapters 4 and 5, cracking in masonry is most often
                              related to the expansion and contraction caused by changes in
                              moisture content. The walls of residences are relatively short in
                              length compared to most commercial construction, so there is less
                              accumulated movement stress to accommodate. However, stress
                              buildup can occur even in small structures if not properly accom-
                              modated. Brick masonry expansion joints should be located near




                   Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
                              Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
                               Any use is subject to the Terms of Use as given at the website.
   272   273   274   275   276   277   278   279   280   281   282