Paving

             290   CHAPTER EIGHT



                              allow for the thickness of the driveway slab and the drainage layer,
                              plus the height of the curb. The concrete thickness tapers down from
                              the edge of the curb to the flat surface of the driveway.
                                 Start pouring concrete in the farthest corner of the forms. As soon as
                              the first few feet of the driveway are poured, begin striking off or screeding
                              the surface level with the top of the forms. Use a length of 2   4 that is
                              slightly wider than the forms. For wide driveways, a 2     6 will be
                              stronger, and a temporary screed may be needed down the middle for
                              striking and leveling drives wider than 20 ft. Continue transporting and
                              dumping and screeding the concrete until the forms are full. The easiest
                              way to do the apron at a street with existing curbs is to set the formwork
                              in two parts. Set temporary formwork at the sides of the flat center section
                              of the apron to use as strike off boards (Figure 8-12). These will be
                              removed as soon as the concrete in the center section is poured and
                              struck, and the concrete in the side sections can be poured immediately
                              afterwards. Shape the tapered concrete at the edges of the driveway apron
                              by hand or with a wood float, tapering it from the top of the street curb
                              and sloping it down into the flat surface of the driveway (Figure 8-13).






















                                                                STRIKE CENTER
                                                                SECTION OF
                                                                                  TEMPORARY
                                                                CONCRETE
                                                                                  SIDE FORM
                                                                LEVEL WITH
                                                                SIDE FORMS
                                FIGURE 8-12
                              Driveway apron forms.



                   Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
                              Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
                               Any use is subject to the Terms of Use as given at the website.
   286   287   288   289   290   291   292   293   294   295   296