Page 44 - Masonry and Concrete
P. 44

Concrete Construction Techniques
                                                                                             43
                                                          CONCRETE CONSTRUCTION TECHNIQUES


            using a convenient unit of measure such as a plastic bucket. If the con-
                                              3
            crete will be made with maximum   8-in. aggregate and air-entrained
                                                                            1
            cement, the correct proportions would be one bucket of cement, 2-  4
                                                             1
                            1
            buckets of sand,   2 bucket of coarse aggregate, and   2 bucket of water.
            The proportions remain the same relative to one another, regardless of
            the size of the container used for batching. Depending on the amount
            of moisture in the aggregates, the water content may have to be
            adjusted slightly. Make a small trial batch to check the workability of
            the mix and add more or less water if necessary.


            3.2     Site Preparation

            Site preparation will include a carefully measured layout of the size
            and shape of the concrete, and excavating the existing soil or placing
            structural fill to the required elevation.
            3.2.1 Size and Layout

            The layout for a floor slab or perimeter footings should be very precise
            because it affects the layout of all the work which follows. Once you
            have determined how to position a house on the site, roughly locate
            each corner with wooden stakes, and then erect batter boards two to
            three feet beyond the corners on each side (Figure 3-4). Use 2   4s for
            the batter board stakes and 1   4s for the crosspieces. Drive the stakes
            well into the ground and use braces if needed to secure them against
            displacement from accidental bumps. If the site slopes, begin at the
            highest corner of the building area and set the top of the first cross-
            piece at 24 in. above the ground. Use a transit, a string-and-line level,
            or a water level to mark the elevation on the other batter board stakes
            and then set all of the crosspieces to the same reference elevation.
               Place nails in the tops of the batter boards and run string lines to
            mark the exact size and shape of the concrete (Figure 3-5). Using a
            plumb bob, mark the intersection of the strings by driving a length of
            steel-reinforcing bar into the ground to temporarily mark the exact cor-
            ner of the concrete (Figure 3-6). Repeat this process at every inside and
            outside corner, being sure to square each corner so that the dimensions
            required by the drawings are exactly the same as those marked on the
            ground. If the last dimension in the perimeter does not match the
            drawings, then one or more of the corners is not square.



                   Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
                              Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
                               Any use is subject to the Terms of Use as given at the website.
   39   40   41   42   43   44   45   46   47   48   49