Page 209 - Plant design and economics for chemical engineers
P. 209

COST  ESTIMATION  183
      TABLE 17
      Ratio factors for estimating capital-investment items based on  delivered-
      equipment cost
      Values presented are applicable for major process plant additions to an existing site where the
      necessary land is available through purchase or present ownership.? The values are based on
      fixed-capital investments ranging from under $1 million to over $20 million.
                                             Percent of deliveredequipment cost for

                                          Solid-       Solid-fluid-  Fluid-
                                          processing   processing  processing  ,
      Item                                plant$       plant  $    plant  $


                                     Direct costs
      Purchased  equipment-delivered  (including            \
       fabricated equipment and process machinery)  0  100  100    100
      Purchased-equipment  installation    45           39          47
      Instrumentation  and  controls  (installed)  9    13          18
      Piping (installed)                   16           31          66
      Electrical  (installed)              10           10          11
      Buildings (including services)       25           29          18
      Yard improvements                    13           10          10
      Service facilities (installed)       40           55          70
      Land (if purchase is required)        6            6           6

         Total direct plant cost          264          293         346
                                   Indirect costs
      Engineering and supervision          33           32          33
     Construction  expenses                39           34          41

         Total direct and indirect plant costs  336    359         420
     Contractor’s fee (about 5% of direct and
       indirect plant costs)               17           18          21
     Contingency (about 10% of direct and
       indirect plant costs)               34           36          42

         Fixed-capital  investment        387          413         483
     Working capital (about 15% of total capital
       investment)                         68           74          86
         Total capital investment        455           487         569

         t Because of the extra expense involved in supplying service facilities, storage facilities, loading
     terminals, transportation facilities, and other necessary utilities at a completely undeveloped site,
     the fved-capital investment for a new plant located at an undeveloped site may be as much as
      100 percent greater than for an equivalent plant constructed as an addition to an existing plant.
         $  See Table 8 for definition of types of process plants.
         Fj  Includes pumps and compressors.
   204   205   206   207   208   209   210   211   212   213   214