Page 210 - Plant design and economics for chemical engineers
P. 210

184  PLANT DESIGN AND ECONOMICS FOR CHEMICAL ENGINEERS

      TABLE 18
      Lang multiplication factors for estimation of
      fixed-capital investment or total capital investment
      Factor  x  delivered-equipment cost = fixed-capital investment
      or total capital investment for major additions to an existing
      plant.
                                 I        Factor for
                                  I          I  Total  capital
                                   Fixed-capital
      Type of plant                investment  investment           I
                            ----I            I                      I
      Solid-processing  plant     I   3.9    I    4.6               \
      Solid-fluid-processing  plant   4.1         4.9
      Fluid-processing  plant         4.8         5.7



      process plant may be obtained by multiplying the basic equipment cost by some
      factor to approximate the capital investment. These factors vary depending
      upon the type of process plant being considered. The percentages given in
      Table 17 are rough approximations which hold for the types of process plants
      indicated. These values, therefore, may be combined to give Lang multiplication
      factors that can be used for estimating the total direct plant cost, the fixed-capital
      investment, or the total capital investment. Factors for estimating the fixed-
      capital investment or the total capital investment are given in Table 18. It
      should be noted that these factors include costs for land and contractor’s fees.
           Greater accuracy of capital investment estimates can be achieved in this
      method by using not one but a number of factors. One approach is to use
      different factors for different types of equipment. Another approach is to use
      separate factors for erection of equipment, foundations, utilities, piping, etc., or
      even to break up each item of cost into material and labor factors.? With this
      approach, each factor has a range of values and the chemical engineer must rely
      on past experience to decide, in each case, whether to use a high, average, or
      low figure.
           Since tables are not convenient for computer calculations it is better to
      combine the separate factors into an equation similar to the one proposed by
      Hirsch and Glazier+
                        C,=f,[W  +.fF+fp+.fJ+~i+~]                       (4)




       tFurther discussions on these methods may be found in W. D. Baasel, “Preliminary Chemical
       Engineering Plant Design,” American Elsevier Publishing Company, Inc., New York, 1976; S. G.
       Kirkham,  Preparation and Application of Refined Lang Factor Costing Techniques,  AACE  Bul.,
       15(5):137  (Oct.,  1972);  C. A. Miller, Capital Cost Estimating-A Science Rather Than an Art, Cost
      Engineers’ Notebook,  AXE  A-1666 (June, 1978).
       $J.  H. Hirsch and E. M. Glazier, Chem.  Eng. Progr.,  56(12):37  (1960).
   205   206   207   208   209   210   211   212   213   214   215