Page 172 - Moving the Earth_ The Workbook of Excavation
P. 172

BASEMENTS

                   4.12   THE WORK







































                               FIGURE 4.12  Three-pile system.


                               basement is dug by the three-pile or open-front method, the procedure shown in Fig. 4.12 may be
                               followed. The first layer is not cut quite to the ends of the excavation, (A), and the ramps built in
                               reaching the bottom are inside the digging lines, (B). They are cut back to the steepest practicable
                               grades on the last pushes, and then one ramp, a foot or so wider than the machine, is cut into the
                               bank. All soil left inside the digging line is then removed by being picked up and carried or pushed
                               out the slot ramp.
                                 The machine can carry a larger load up the ramp when moving forward than when reversing.
                               This is because it is nose-heavy when loaded, a condition which is made worse in backing up an
                               incline, both by the shift of the center of gravity toward the front and by the reaction from the driving
                               torque which pushes the front down. In ascending a grade forward, both of these forces tend to raise
                               the front and improve stability. These effects become more pronounced as the incline becomes
                               steeper.
                                 Turning around in a small excavation may be difficult, or impossible, so that it is often better
                               to back out with a small load than to take the time to turn in order to carry a larger one.

                               Cutting Walls.  So far as possible, the excavation should be finished with vertical walls. Long
                               ones may be cut neatly by digging parallel to the edge, but because of limited space, much finishing
                               must be done by working straight toward the digging line.
                                 Until the line is reached, the bank digging procedures in Chaps. 10 and 16 may be followed.
                                 A vertical face may be cut by allowing bank resistance to move the tractor back as the bucket
                               rises. This may be managed by slipping the clutch with mechanical drive, or slowing the engine
   167   168   169   170   171   172   173   174   175   176   177