BASEMENTS

                                                                                           BASEMENTS   4.21


















                                                  FIGURE 4.19  Haulaway basement job.








































                                          FIGURE 4.20  Starting large basement.

                                  from the curb, will touch an existing store building on the east, a 12-foot driveway backed by
                                  another building on the west, and a proposed parking lot. The footings of the east building are
                                  below the 18-foot level, those on the west are 12 feet below the surface.
                                    The site has been cleared, but two large stumps have been left. The topsoil is of such poor quality
                                  that it will not be separated. The contractor owns a three-quarter yard shovel with dipper, backhoe,