Page 38 -
P. 38

DESIGN AND CONSTRUCTION                  3.3


         •  To what extent must the  existing facilities be brought up to  current design standards
          and building codes  as part of the project?
         •  How can the original design, as-built facilities, and current condition be defined, and
          remaining useful life of existing facilities and structures  be determined?
         •  How  can the  existing treatment facilities be  kept  in reliable service during the  con-
           struction of plant modifications and be integrated with the new facilities?
         •  What safety  or environmental hazards  (such  as lead paint, asbestos  insulation, and un-
          derground petroleum spills)  may be uncovered during the construction of the  modifi-
          cations?
         •  What provisions have been previously made in the plant to expand or upgrade the ex-
          isting facilities?
         •  Are there  any existing plant site or hydraulic constraints that must be taken into con-
          sideration with the facilities improvements?

           Design  decisions  on  these  issues  often  require  reasonable  compromises  that  must
         be  worked  out  among the  design team,  the  owner,  and regulatory agencies. The  cost-
         effectiveness  of  modifying each  existing  plant  component versus  constructing a  new
         component should be considered.



         Custom-Built Equipment versus Preengineered versus Package
        When the treatment plant under design has a capacity of less than about 10 million gal-
         lons per day (mgd), it is often possible to choose between custom-designed, preengineered,
         or "package"  treatment units. In custom-designed units, major processes  usually utilize
        reinforced concrete construction. The design engineer is responsible for all dimensions of
         the unit and the complete process  electrical,  mechanical, and structural  design. Equipment
         suppliers  provide and are responsible for design and performance of specific  equipment
         such as weirs,  gates,  sludge  collectors,  and other equipment located in the process unit.
           Preengineered units are  generally made using steel  or fiber-reinforced plastic tanks.
         An equipment supplier takes  responsibility for the full process,  structural,  electrical,  and
         mechanical design of the unit. The design engineer generally is responsible only for the
         foundation design and items  such  as  influent water  quality, hydraulic, and mechanical
         connections, electrical  and instrumentation connections, and, if required,  buildings or en-
         closures to house the process  unit. Preengineered units are strictly  field-assembled.
           Package units are partially or completely factory-assembled and installed on the site.
         The package  units are  often  skid-mounted, with the  process  components prepiped  and
         prewired,  requiring minimal fieldwork to install. The package units are often restricted  to
         1 to 2 mgd in capacity,  as the size of the unit is constrained by shipping limitations.
           Custom-designed process  units tend to have higher construction costs but lower main-
         tenance needs and longer useful lives. The best decision for a specific project can be made
         only after a careful analysis of the costs  and benefits of each feasible alternative. In gen-
         eral, as the plant capacity becomes smaller, preengineered and package units become more
         cost-effective  and require less time to construct.



         Design Development
         As  part  of  the  preliminary  design  phase,  several  key  design  parameters  must  be
         developed:
   33   34   35   36   37   38   39   40   41   42   43