Page 66 -
P. 66

2 - ORGANIZATIONAL INFLUENCES AND PROJECT LIFE CYCLE






                         The generic life cycle structure generally displays the following characteristics:

                           •   Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the
                              project draws to a close. Figure 2-8 illustrates this typical pattern.
                           •   The typical cost and staffing curve above may not apply to all projects. A project may require significant
                              expenditures to secure needed resources early in its life cycle, for instance, or be fully staffed from a point
                              very early in its life cycle.
                           •   Risk and uncertainty (as illustrated in Figure 2-9) are greatest at the start of the project. These factors
                              decrease over the life of the project as decisions are reached and as deliverables are accepted.
                           •   The ability to influence the final characteristics of the project’s product, without significantly impacting
                              cost, is highest at the start of the project and decreases as the project progresses towards completion.
                              Figure 2-9 illustrates the idea that the cost of making changes and correcting errors typically increases
                              substantially as the project approaches completion.

                         While these characteristics remain present to some extent in almost all project life cycles, they are not always
                      present to the same degree. Adaptive life cycles, in particular, are developed with the intent of keeping stakeholder
                      influences higher and the costs of changes lower throughout the life cycle than in predictive life cycles.




                                     High
                                           Risk and uncertainty






                                       Degree






                                           Cost of changes


                                     Low
                                                                Project Time


                                              Figure 2-9. Impact of Variable Based on Project time
















             40       ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   61   62   63   64   65   66   67   68   69   70   71