Estimation of Ventilation Air Quantity                             45
































           Figure 4.1 A typical modern coal mine layout.


           year. Economy of size drives the cost of production further down, but the capital cost
           goes up. A very large coal mine may cost $500 million to open up today and produce
           12 to 15 million tons of coal per year.



           4.2   Methane Emissions

           It is safe to assume that all coal seams are gassy because coal and methane in coal are
           syngenetic in origin; that is, they are derived from the same plant material. The gas
           content of coal seams varies depending on the rank of coal and the depth of coal
           seam. Globally, coal seams can be divided into three categories depending on the depth
                                 3
           and their gas contents in ft /ton as shown in Table 4.1.

                 Table 4.1 Gassiness of Coal Seams [1]

                                                                   3
                  Category             Depth (ft)      Gas Content (ft /ton)
                  Mildly gassy         500 or less     100 or less
                  Moderately gassy     500e1500        100e300
                  Highly gassy         1500e3000       300e700