Page 226 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 226

cost contributions are not dependent on any of the estimating factors provided in Table 8.2. Therefore, the
                    manufacturing cost is generally insensitive to the estimating factors provided in Table 8.2. The use of the
                    midrange values is acceptable for this situation.


                    8.2 Cost of Operating Labor





                    The technique used to estimate operating labor requirements is based on data obtained from five chemical
                    companies  and  correlated  by Alkayat  and  Gerrard  [4]. According  to  this  method,  the  operating  labor
                    requirement for chemical processing plants is given by Equation 8.3:


                    (8.3)








                    where N  is the number of operators per shift, P is the number of processing steps involving the handling
                              OL
                    of  particulate  solids—for  example,  transportation  and  distribution,  particulate  size  control,  and
                    particulate  removal. N   is  the  number  of  nonparticulate  processing  steps  and  includes  compression,
                                              np
                    heating and cooling, mixing, and reaction. In general, for the processes considered in this text, the value of
                    P is zero, and the value of N  is given by
                                                    np

                    (8.4)








                                                                         compressors
                                                                         towers
                                                                         reactors
                                                                         heaters
                                                                        exchangers


                    Equation 8.3 was derived for processes with, at most, two solid handling steps. For processes with a
                    greater number of solid handling operations, this equation should not be used.


                    The value of N  in Equation 8.3 is the number of operators required to run the process unit per shift. A
                                     OL
                    single operator works on the average 49 weeks a year (3 weeks’ time off for vacation and sick leave),
                    five 8-hour shifts a week. This amounts to (49 weeks/year × 5 shifts/week) 245 shifts per operator per
                    year. A chemical plant normally operates 24 hours/day. This requires (365 days/year × 3 shifts/day) 1095
                    operating  shifts  per  year.  The  number  of  operators  needed  to  provide  this  number  of  shifts  is  [(1095
                    shifts/yr)/(245 shifts/operator/yr)] or approximately 4.5 operators. Four and one-half operators are hired

                    for each operator needed in the plant at any time. This provides the needed operating labor but does not
                    include any support or supervisory staff.
   221   222   223   224   225   226   227   228   229   230   231