Page 254 -
P. 254

Underbalanced Drilling Operations                             217


        and better pressure stability control at the bottomhole. However, running in
        casing with a parasite tubing string is difficult.
           The second annulus injection method is the parasite casing injection
        method shown in Figure 10.5. The outer casing can be set and cemented
        beyond the vertical section. The inner casing is set but is not cemented.
        Gas is injected into the drill string–inner casing annulus through the
        inner–outer casing annulus. The inner-casing string is usually retrieved
        after drilling. With this gas injection method, only a portion of the cased
        hole section of the annulus is aerated. It again allows for the use of con-
        ventional MWD and better pressure stability control at the bottomhole.
        However, complications can occur due to the nonconstrained, noncentralized
        inner casing at the bottom.
           The third annulus injection method is the through completion injec-
        tion method shown in Figure 10.6. The outer casing can be set and








































        Figure 10.5 Parasite casing gas injection method.
   249   250   251   252   253   254   255   256   257   258   259