Page 55 -
P. 55

Assemble tasks
                          After the estimation meeting is finished, the project manager works with the moderator to
                          gather all of the results from the individual preparation and the estimation session. The
                          project manager removes redundancies and resolves remaining estimate differences to
                          generate a final task list, with effort estimates attached to each task. The assumptions are
                          then summarized and added to the list.
                          The final task list should be in the same format as the individual preparation results (see
                          Figure 3-1). In addition, the project manager should create a spreadsheet that lists the
                          final estimates that each person came up with. The spreadsheet should indicate the best-
                          case and worst-case scenarios, and it should indicate any place that further discussion will
                          be required. Any task with an especially wide discrepancy should be marked for further
                          discussion. Figure 3-5 shows an example of a spreadsheet that summarizes the results. It
                          contains a column for each estimator, as well as columns for the best-case estimate (using
                          the lowest estimates, which assume that everything has gone well), worst-case estimate
                          (using the highest estimates, which assume that the project hit many roadblocks), and
                          average estimate. (When the project manager calculates these numbers, it’s often a good
                          idea to remove the highest and lowest estimates in order to eliminate outliers.)

                               Goal statement To estimate the time to develop prototype for customers A & B
                               Estimators  Mike, Quentin, Jill, Sophie              Units days
                                                                            Shaded items must be discussed
                            WBS# or                            Best- Worst- Avg.-
                            priority  Task name     M. Q. J.  S. case case  hi & lo  Notes
                            1      Interview customers (A+B)  6  4  3  3  3  6  3.5
                            2      Develop requirements docs 5  10 2  5  2  10  5  Discrepancy between Q. and J.
                            3      Inspect requirements docs  7  5  6  5  5  7  5.5
                            4      Do rework        8  7  9  7  7  9    7.5
                            5      Prototype design  28 23 31 25  23  31  26.5
                            6      Test design      9  7  6  6  6  9    6.5

                                               Total  63 56 57 51  46  72  54.5

                          FIGURE 3-5. Summarized results of estimation
                          The assumptions should also be put into a final form, suitable for inclusion in the
                          “Assumptions” section of the vision and scope document. (If the author of the vision and
                          scope document is not the project manager, then the project manager should turn the
                          assumptions over to the author and help incorporate them into the document.) If the
                          vision and scope document was already inspected and approved, it should be updated and
                          then inspected again prior to being used as the basis for a project plan.






                                                                                              ESTIMATION  47
   50   51   52   53   54   55   56   57   58   59   60