Page 172 - Beyond Decommissioning
P. 172

Experience and lessons learned                                    153

           employed in the dismantling (Fig. 6.8). Physical decommissioning was completed in
           March 1996, and the final radiation survey was completed in October 1996.The dura-
           tion of physical decommissioning work was 43 months, which in comparison with
           subsequent NPP decommissioning projects lasting 10 years or more can be considered
           a major achievement. FSV was the first commercial US NPP to be decommissioned.
              The nuclear reactor and associated systems were demolished and turbine, conden-
           sate systems and associated buildings were reused as part of a gas-fired power plant
           with the addition of a “topping turbine” (a separately fossil-fired boiler system to gen-
           erate high-temperature steam and turbine). The first gas combustion turbine was
           installed in April 1996, just 1 month following the completion of physical decommis-
           sioning; the final radiation survey was still underway at the time. Incidentally, this is a
           good example of planning and implementing conversion in parallel to decommission-
           ing. In 2001, two more turbines were added to the plant. The current combined-cycle
           operation is based on the following principle: the waste heat from the gas turbine is
           utilized to produce secondary steam, which runs the original plant’s steam turbine to
           produce extra power. As quoted by (HPS, 2003) the electric capacity of FSV increased
           to 710 MW (HPS, 2003).
              The Army Corp of Engineers is planning the dismantling of Fort Greely’s SM-1A,
           the only NPP ever installed in Alaska. The SM-1A plant provided steam and electric-
           ity to the Army base between 1962 and 1972. It was one of eight projects to test the use
           of small NPPs at remote locations. SM-1A was eventually shut down because it was
           costlier to operate than a conventional diesel power plant. After shut down in 1972, the
           Army placed it into safe enclosure. The spent fuel and waste were shipped away and
           the radioactive components of the reactor were encased in cement.


























           Fig. 6.8 Decommissioning job at Fort St. Vrain NPP.
           Courtesy of NRC.
   167   168   169   170   171   172   173   174   175   176   177