Page 344 - Beyond Decommissioning
P. 344

320                                                Beyond Decommissioning

         The Site’s Nuclear License requires that the licensee supervise the safety of the tenants
         in some circumstances. To facilitate compliance, the licensee has established
         tenant safety requirements which are based on its own internal safety requirements
         (Neal, 2003).
            The latest news at the time of writing (May 2018) is based on Magnox (2016) and
         SSG (2017). The Winfrith decommissioning program assumed the reaching an interim
         end state (IES, a phrase used in the United Kingdom to mean the end of all physical
         works) around 2023. The reference to physical work is important because after the
         physical work, natural processes (e.g., radioactive decay and natural degradation of
         contaminants) will continue to work toward reaching the site end state (SES). The
         original plan was to remove all radioactivity and release the site as publicly open heath
         land. The projected use has not changed but the detailed description of the SES and the
         plan to deliver it are still under discussion. There could be opportunities to reduce the
         amount of physical work now, and leave some residual contamination in situ. This
         could also have the benefit of reducing the amount of material that will need to be
         imported to the site to bring about the IES. For example, the current view is to leave
         behind the basement of SGHWR and DRAGON and backfill with very low-level
         (radioactive) waste (VLLW) resulting from the demolition of structures. However,
         without the changes in the law, the site will remain a nuclear licensed site (in the
         writer’s view, a form of restricted release).


         7.10    Harwell Southern Storage Area, United Kingdom

         The Harwell Southern Storage Area (SSA) (referred locally as the “Bomb Dump”)
         deserves a more detailed analysis. This 7-ha area, contiguous to the Chilton Primary
         School, and just 1km off the Harwell (formerly) nuclear research center, was origi-
         nally used as a WWII ammunitions storage area by the UK’s Royal Air Force
         (RAF) and subsequently for RAW handling and for the burial of chemical, low-level
         radioactive and beryllium contaminated waste by Harwell’s nuclear operator,
         UKAEA. There are also dwellings and a farm in the vicinity. The SSA consisted
         of open ground, small huts, concrete trackways, and several large earth mounds
         around the original bomb storage bays. The main hazards were due to waste dumped
         in four separate disposal pits. The contamination included hazardous chemicals, a
         wide range of radionuclides (plutonium, uranium, strontium, etc.) together with beryl-
         lium, which is chemically toxic.
            Preliminary decontamination of the SSA was conducted to eliminate the need for
         the site to be licensed under the Nuclear Installations Act (as required for the main
         Harwell site). However, this remediation was not sufficient to allow unrestricted
         access; instead the site remained subject to security. Remediation continued in the
         1990s and was completed in 2002. A post-remediation report was drafted to record
         all the details of the project. Following extensive site monitoring, the area was land-
         scaped and top soiled. Subsequently, the land was approved by the local government
         as suitable for recreational or residential purposes. Redevelopment will be undertaken
         by a private commercial developer. Given the site vicinity to inhabited areas, public
   339   340   341   342   343   344   345   346   347   348   349