Page 101 - Buried Pipe Design
P. 101

Design of Gravity Flow Pipes  77

         migrate from trench wall into the embedment, the trench wall may
         settle, but the pipe is unaffected. If embedment particles migrate into
         the trench wall, the shift in sidefill support may allow slight ring
         deflection. This could occur only if the trench wall soil is loose enough,
         or plastic enough, that the embedment particles can migrate into it.
         Soil particle migration is unusual, but must be considered. Remedies
         include (1) embedment with enough fines to filter out migrating parti-
         cles in groundwater flow and (2) trench liners. Geotextile liners may
         be required under some circumstances.


         Voids in the embedment
         Soil should be in contact with the pipe in order to avoid piping (chan-
         nels of groundwater flow) under the haunches. Voids are avoided if the
         embedment is flowable fill—a good idea when trench widths are too
         narrow for placement of soil under the haunches. Trench boxes and
         sheet piling should be designed so tips of the piles or shield are above
         the spring lines of the pipe. If they are designed and used properly,
         voids left by the withdrawal of sheet piling or trench shield will not
         affect the performance of the pipe.


         Heavy equipment
         If the buried structure has a low inherent strength or is so flexible that
         heavy compactors can deform it, then only light compactors can be
         used close to it. Heavy compactors must remain outside of planes tan-
         gent to the structure and inclined at an angle less than 45°   
/2 from
         horizontal. Soil cover H greater than minimum is required above the
         structure. The heavy equipment zone is often specified and is usually
         2 ft or D/2, whichever is greater. Operators should be reminded that a
         large structure gives a false illusion of strength. It achieves its
         strength and stability only after the embedment has been placed about
         it. Because the structure cannot resist high sidefill pressures during
         soil placement, operators should think, “If it were not there, how far
         back from the edge of the sidefill would I keep this equipment in order
         not to cause a soil slope failure?” The answer is found from experience
         and from the tangent plane concept.  A margin of safety is usually
         applied to the 45°   
/2 plane by specifying a 45° tangent plane. The
         minimum cover H min for various types and weights of equipment can
         be determined by the methods suggested in Chap. 2.  As a rule of
         thumb, the minimum soil cover should not be less than 3 ft for H-20
         truck loads, D8 tractors, etc. For scrapers and super-compactors, 5 ft
         of soil may be a more comfortable minimum.
   96   97   98   99   100   101   102   103   104   105   106