The spanning 2 X 4s are drilled at eithe r end to accommodate bolts
that will be used to attach them to the uprights. The location of the
bolt holes is determined by the distan ce between the ce nters of the
guide rails mounted on the frame beam s (see Figure 7.4).
Figure 7.4
Finding mounting hole
location for spanning
beams.
The uprights will need to be drilled to allow the ce nter of eac h
spanning beam to be at the ce nte r of the rails that will be installed
along thei r length (see Figure 7.5).
Figure 7.5
Location of mounting
holes on uprights.
Also drill two access holes on the outs ide of each of the uprights
to allow the install ati on of the bolts (see Figure 7.6).