Page 272 - Chemical engineering design
P. 272

247
                                        COSTING AND PROJECT EVALUATION
                   Example 6.1
                   The purchased cost of a shell and tube heat exchanger, carbon shell, stainless steel tubes,
                                       2
                   heat transfer area 500 m , was £7600 in January 1998; estimate the cost in January 2006.
                   Use the Process Engineering plant index.
                   Solution
                   From Figure 6.1:
                     Index in 1998 D 106
                             2000 D 108, 100 (change of base)
                             2004 D 111
                   So, estimated cost in January 2000 D 7600 ð 108/106 D £7743,

                   and in 2004 D 7743 ð 111/100 D £8595
                   From Figure 6.1, the average increase in costs is about 2.5 per cent per year. Use this
                   value to predict the exchanger cost in 2006.
                                             2
                   Cost in 2006 D 8595 ð  1.025  D £9030
                                                    Say £9000.


                           6.5. RAPID CAPITAL COST ESTIMATING METHODS

                   6.5.1. Historical costs
                   An approximate estimate of the capital cost of a project can be obtained from a knowledge
                   of the cost of earlier projects using the same manufacturing process. This method can be
                   used prior to the preparation of the flow-sheets to get a quick estimate of the investment
                   likely to be required.
                     The capital cost of a project is related to capacity by the equation
                                                              n

                                                           S 2
                                                 C 2 D C 1                                6.2
                                                           S 1
                   where C 2 D capital cost of the project with capacity S 2 ,
                         C 1 D capital cost of the project with capacity S 1 .
                   The value of the index n is traditionally taken as 0.6; the well-known six-tenths rule. This
                   value can be used to get a rough estimate of the capital cost if there are not sufficient data
                   available to calculate the index for the particular process. Estrup (1972) gives a critical
                   review of the six-tenths rule. Equation 6.2 is only an approximation, and if sufficient data
                   are available the relationship is best represented on a log-log plot. Garrett (1989) has
                   published capital cost-plant capacity curves for over 250 processes.


                   Example 6.2
                   Obtain a rough estimate of the cost of a plant to produce 750 tonnes per day of sulphuric
                   acid, from sulphur. Use the costs given by Garrett (1989) reproduced in Figure 6.2.
   267   268   269   270   271   272   273   274   275   276   277