Page 86 -
P. 86

Overview     65







































               FIGURE 6-8
               Typical Roles on the DG Team.


               pose. You will start to run into politics, ignorance, and even resistance at this point. Here are some
               symptoms that the team is not taken seriously:
               • Viewing the DG team as the programmer “graveyard”dusually IT staff are the first members of the
                  DG team. Often, individuals will be submitted for membership because they do not fit anywhere
                  else. This means someone is not taking DG seriously. The DG deployment team needs to be
                  experienced in internal politics, know the players, and be able to think outside traditional
                  information-management functionality. Typical roles are shown in Figure 6-8.
               • Getting a steering committee that immediately delegates attendance to non-decision makers. Again,
                  DG is not being taken seriously. More education is required, so add it to the plan.

               Approach Considerations

               There are two alternatives when the rollout team runs into obstacles. Note we said when, not if.
               1. As part of an MDM or similar effort, the project sponsor discovers a brand-new issue that is related
                  to the DG program. (Normally, it is something along the lines of “No, you cannot use that resource
                  anymore.”) The DG team needs to submit an issue to the PMO or similar body over the MDM
                  project. This is one of those weird transitional things that happen, but it will certainly occur.
   81   82   83   84   85   86   87   88   89   90   91