Page 29 - Forensic Structural Engineering Handbook
P. 29

1.10              DESIGN AND CONSTRUCTION PRACTICES

           architect or the structural engineer does not take exception to the above during the bid period,
           then the architect/engineer (A/E) must abide by the above or take the risk of receiving a delay
           claim from the contractor.]
             There have been many discussions regarding the party who is legally responsible for the
           design and detailing of steel connections during the review/approval process of the shop draw-
           ings since the Hyatt Regency walkway collapse in Kansas City, Missouri in 1981. The gener-
           ally accepted version is that the structural engineer of record (SER) is responsible for the entire
           structure and its component parts unless the designer specifically provides sufficient informa-
           tion (i.e., forces; including reactions and moments) on the contract documents and instructs the
           contractor (detailer) to assume the responsibility for the design of certain designated connections
           and/or members. Further, the SER would be prudent to stipulate that items not so designed by
           the SER be designed by a professional structural engineer registered in the state where the pro-
           ject is constructed and engineering calculations be submitted for the SER’s review.
             Table 1.4 is a checklist prepared by CASE and can be used by forensic engineers in their inves-
           tigation.Figure1.1 illustrates a typical shop drawing review stamp used by various structural engi-
           neering consultants upon the recommendation of insurance carriers. Figure 1.2 is a sample of a
           stamp used by a consultant in order to designate responsibility that is assigned to the contractor
           regarding “the means and methods of construction,” which generally includes the following:
             Underpinning of existing adjacent structures
             Design of formwork for concrete construction





































                  FIGURE 1.1 Typical shop drawing review stamp.
   24   25   26   27   28   29   30   31   32   33   34