Page 322 - Forensic Structural Engineering Handbook
P. 322

TEMPORARY STRUCTURES IN CONSTRUCTION         10.11

             The Designer
             The design professional is responsible for the accuracy and adequacy of her or his plans and
             specifications. By distributing these documents for use, the design professional impliedly
             warrants to both the owner and contractor that a cohesive structure will result, provided the
             plans and specifications are followed. But the designer does not guarantee perfection, only
             that he or she exercised ordinary care. When a contractor who properly follows the designer’s
             documents experiences a problem, liability will ultimately rest with the architect or engi-
             neer. The designer would be responsible for all additional costs of construction attributable
             to faulty design: the cost of all resultant damage, and the cost of redesign. This includes lia-
             bility to third parties for injuries, death, and property damage.
               A design professional has no duty to supervise, inspect, or observe the performance of
             the work she or he designed, absent a duty which the design professional has assumed by
             contract, by statute, or by having filed plans with a local building department. Once some
             duty has been assumed, however, state courts are in wide disagreement as to the extent of
             responsibility and liability. Some courts have found that design professionals have a non-
             delegable duty to regularly supervise the means and methods of construction. At the very
             least, the architect or engineer will be responsible for making occasional visits to the site to
             verify technical compliance with the contract documents.
               Designers should be wary of so-called routine sign-offs of the contractor’s work. The
             sign-off may include a certification by the designer that the contractor has complied with
             the plans and specifications and with applicable codes. Such a certification could impose
             on the designer liability equal to the contractor’s in the event of a failure.
               An engineer of record (ER) should be particularly careful in requiring submission of
             and in “approving” the contractor’s detailed plan for temporary construction.
             Exculpatory language is often placed on the engineer’s “approval” stamps to the effect
             that the engineer has assumed no responsibility by having reviewed the submission. In
             the event the design was not adequate and there was injury to person or property, it is
             likely that the engineer’s stamp would not be sufficient to exculpate him or her from lia-
             bility to injured third parties. The engineer of record should, but often does not, have
             adequate familiarity with the materials, hardware, and equipment, or the experience
             with methods of installation of temporary structures. If the engineer of record does not
             have the necessary expertise, or does not intend to carefully review each and every sub-
             mission, the submission should not be required at all. “Don’t ask for it, if you don’t know
             what to do with it.”


             The Contractor

             The ambit of the contractor’s responsibility is far-reaching. The contractor is responsible
             for performing all required work in accordance with the contract documents, generally
             accepted construction practices, and governing legislative enactments. In sum, no matter
             what goes wrong, the contractor stands suspected, accused, delayed, and eventually is
             likely to pay or at least share the resulting costs.
               It is important to stress that it is not necessarily enough that the contractor has performed
             to the best of her or his own ability. When assessing liability, the courts do not simply
             accept at face value what the contractor did, but measure that against what an ordinary con-
             tractor of similar experience would have done under similar circumstances. Consequently,
             when determining whether a contractor exercised ordinary or reasonable care in doing the
             work, the court will look at how that work compares to the degree of skill prevalent in the
             industry at the time the work was performed.
   317   318   319   320   321   322   323   324   325   326   327