Page 162 - Green Building Through Integrated Design
P. 162

138   COSTS OF GREEN BUILDINGS




                      PLATINUM PROJECT PROFILE
                      Hawaii Gateway Energy Center, Kailua-Kona, Hawaii
                      Designed to house research, development, and demonstration facilities for the
                      Natural Energy Laboratory of Hawaii, the Hawaii Gateway Energy Center was
                      completed in January 2005. The 3600-square-feet facility’s total project cost
                      was $3.4 million.* Designed to be a thermal chimney, the building captures heat
                      and creates air movement using only the building’s form along with thermo-
                      dynamic principles. The project has a ventilation rate of 10 to 15 air changes
                      per hour without the use of a mechanical system. A 20-kilowatt photovoltaic
                      system provides all the energy needs. The building was designed to be 80 percent
                      more energy efficient than a comparable facility built to ASHRAE 90.1-1999
                      standards. †





                     SOFT COSTS FOR GREEN BUILDING PROJECTS
                     The 2004 GSA study mentioned earlier also looked at “soft costs,” costs for things
                     that are not part of building construction. The study estimated soft costs for addi-
                     tional design and documentation services ranged from about $0.40 to $0.80 per
                     square foot (0.2% to 0.4%) for the courthouse and $0.35 to $0.70 per square foot
                     (0.3% to 0.6%) for the office building modernization project. One caution: the
                     added percentage of total cost may be higher for smaller projects.
                       Therefore, each building team should look at every cost that a project would
                     incur, from permitting and site development to furniture and fixtures, before decid-
                     ing that a particular green measure is “too costly.” Integrated design requires sys-
                     tems thinking, to avoid the near universal tendency to look at individual cost items
                     in isolation, a process euphemistically called “value engineering.” Deciding which
                     costs are going to provide the highest value in a given situation should be a primary
                     task of the architect, working in concert with the client, the building owner or
                     developer, and the builder.
                       One thing is certain: there are costs associated with green building projects
                     that need to be taken into account, especially with those aiming at LEED certi-
                     fication. Many projects do not consider these costs especially onerous, but some
                     do. Table 7.3 shows some of the potential “soft” costs, that is, those not con-
                     struction related. Some of these costs should be considered essential to good
                     project design and execution, specifically building commissioning and energy
                     modeling, while others are more clearly associated with the LEED certification
                     effort.


                     *This is obviously a high-cost project owing to the many special features included.
                     † U.S. Green Building Council, http://leedcasestudies.usgbc.org/overview.cfm?ProjectID=592, accessed April 2008.
   157   158   159   160   161   162   163   164   165   166   167