Page 24 - Highway Engineering Handbook Building and Rehabilitating the Infrastructure
P. 24

ENVIRONMENTAL ISSUES                      7


                                                     Proposed Agency
                                                         Action



                                                   Categorical Exclusion or
                                                      Other Exemption

                                       Exclusion                       No
                                        Applies                      Exclusion


                                                                   Environmental
                                                                    Assessment

                                                              No              EIS
                                                              EIS           Required

                                                                                Notice of Intent

                                                                               Scoping Process


                                                                                  Draft EIS


                                                                                Agency/Public
                                                                              Review & Comment


                                                       Finding of No              Final EIS
                                                     Significant Impact
                                                         (FONSI)
                                                                               Record of Decision


                                 Agency Action         Agency Action            Agency Action
                              FIGURE 1.1 Overview of NEPA environmental review process. (From R. E. Bass and A. I. Herson,
                              Mastering NEPA: A Step-by-Step Approach, Solano Press Books, Point Arena, Calif., 1993, with permission)

                              in Tables 1.2 and 1.3. The following are examples of actions that would trigger the need
                              to comply with NEPA.

                              • The proposed use of federal funds for the planning, engineering, or construction of a pro-
                               ject, or for needed right-of-way acquisition
                              • Modifications to an existing interstate highway
                              • Modifications to a non-interstate access-controlled highway that affects the right-of-way
                               previously financed with federal funds
   19   20   21   22   23   24   25   26   27   28   29