Safety and the Environment                                             89



                              Base Line
                                Study





                               Planned
                               Activity





                                                            Revise planned
                                EIA
                                                               activity




                                                    No
                              Is impact
                             acceptable?


                           Yes




                            Perform Activity


             Figure 5.4  Application of an EIA.


             planned activity (Figure 5.4). This will enable decision makers to determine
             whether an activity is acceptable and if not, identify possible alternatives. Typically,
             EIAs will be carried out for
               seismic
               exploration and appraisal drilling
               development drilling and facilities installation
               production operations
               decommissioning and abandonment.

                To allow objectivity of the findings, EIAs are usually carried out by independent
             specialists or organisations. It will involve not only scientific experts, but also require
             consultation with official and representative bodies such as the government
             ministries for the environment, fisheries, food, agriculture and local water. In
             activities which may impact on local population (terminals, refineries, access roads,
             land developments) agreement with local NGOs may be critical. The EIA process