Page 65 - Offshore Electrical Engineering Manual
P. 65

52     CHAPTER 4  Prime Mover Selection Criteria




                           2.   The effects of any process flares must be taken into consideration, both for hot
                            gas and radiation.
                           3.   The effect of wind on all the various platform exhausts must also be considered.
                            Although the prevailing wind is the most important consideration, the turbine
                            must be able to develop sufficient power in any wind condition, and with any
                            combination of other engines installed on the platform, working at their normal
                            outputs. If the exhaust plume from another engine causes the engine in question
                            to govern down, this may be overcome by the use of extra ducting or a water
                            curtain installed around the exhaust of the other engine.

                            Airflow through the engine, and hence cooling, may be improved by cleaning the
                         compressor section of the engine after a few months of operation. The improvement
                         in output power after routine cleaning is usually significant and can be as much as
                         10% of its rated power. The selectors of the prime mover must take this into account
                         in their rating calculations.
                            If it is necessary to install a load shedding system because of engine power
                         limitations or increasing electrical demand, as mentioned earlier the system should
                         take turbine exhaust temperature into account. If the load shedding system tripping
                         level is based purely on monitoring electrical load for a fixed worst-case value,
                         production operations may be unnecessarily curtailed. In colder weather condi-
                         tions, as much as 15% of extra engine capacity would still be available. This may
                         amount to several megawatts with a 25 MW generator set. The converse is also
                         possible when exceptionally warm weather conditions may reduce engine capacity
                         to below the load shedding system tripping point causing the generator set to trip
                         on underfrequency.


                         GAS INGESTION FROM LEAKS
                         A large gas turbine generator set may take in the region of 30 s from the initiation
                         of an emergency stop signal to slow down to a speed at which reacceleration is no
                         longer viable without cranking. During this period of deceleration, it is vulnerable
                         to ingestion of gas from serious process gas leaks on the platform. Such ingestion of
                         gas in sufficient quantity, bearing in mind that all electrical loads would have prob-
                         ably been removed by the emergency shutdown system by this time, may cause the
                         machine to reaccelerate and overspeed to destruction.
                            The risk of this occurring must be minimised by the following:

                           1.   Carefully siting gas detectors to ensure that serious gas leaks are detected as
                            soon as possible. A ‘2-out-of-N’ voting system should be used to minimise
                            spurious generator trips due to faulty detectors.
                           2.   Governor response to an emergency engine stop signal should be as fast as pos-
                            sible within the metallurgical limitations imposed by turbine blade cooling rates
                            etc.
   60   61   62   63   64   65   66   67   68   69   70