Page 389 - Pipeline Pigging Technology
P. 389

Pipeline  Pigging  Technology


      they pass through the junction. The wye piece has external stiffeners, and the
      web between the incoming bores is cut back and rounded off. This design has
      been successfully manufactured by two routes: both by casting and machin-
      ing the bores,  and also by forging components, welding them together and
      then machining.
         The Ula pipeline has been pigged regularly, at intervals of about every two
      weeks, for wax removal. Cupped pigs with elongated  bodies  are used such
      that there is always at least one set of cups sealing to provide the drive as the
      pig negotiates  the enlarged bore at the wye.
         Statoil has now connected  the  Gyda  pipeline to the spare branch of the
      Ula wye, and has installed a second wye of the  same design in the  Gyda line
      still leaving a connection available for further entrants. This combination of
      two wyes in series has been  successfully  pigged on a regular basis for wax
      removal since Gyda  started exporting oil in June,  1990.
         Statoil has installed a third wye junction, connecting the  16-in  Vestefrikk
      and  Oseberg C pipelines to OsebergA. This reinforces the marked trend for
      those,  such as Occidental and  Statoil, who  already have wye junctions, to
      install more. Two further  operators  are to install wyes, both  of them large-
      diameter. One is to be inserted in the  32-in Frigg  to MCP-01  gas pipeline for
      the Total Bruce project, and the other in the 30-in Beryl pipeline by Mobil. As
      shown in Table 1, these latter are significantly larger than the  16 to 20-in wyes
      presently  in  service.



        RESEARCH AND            DEVELOPMENT



        A comprehensive testing programme was carried out to develop the Statoil
      wye  design  and  prove  its  piggability.  The  tests  were  carried  out  by
      A.R.Reinertsen AS for  the  Statoil Ula project  in  1983-85. They were  based
      initially on a 6-in acrylic plastic water-driven loop, where a variety of types of
      pig were observed passing through a convergent wye [ 1 ]. In the course of 450
      runs, a preferred  concept  for the  wye was  selected  and  the  branch  angle
      optimized. A further  100 runs were then carried out on a full-scale  20-in water-
      driven  loop with a translucent glass fibre wye, demonstrating that conven-
      tional pigs, spheres, welding bladders, and inspection vehicles would all pass
      though  successfully. This bore  design was used  for  Statoil's wyes, and  has
      demonstrated itself to be reliably piggable in operation.
        Testing  programmes  of  wyes  have  also  been  carried  out  by  BHRA  at
      Cranfield and British Gas, believed  to be 4 and 8-in scale model tests and  full-
      scale pull-through tests of on-line inspection  vehicles  respectively.

                                       370
   384   385   386   387   388   389   390   391   392   393   394