        1.  Conceptual Engineering

        The primary objectives are normally:


        -  To establish technical feasibility and constraints on the system design and construction;
        -  To eliminate non viable options;
        -  To identify the required information for the forthcoming design and construction;
        -  To allow basic cost and scheduling exercises to be performed;
        -  To identify interfaces with other systems planned or currently in existence.


        The value of the early engineering work is that it reveals potential difficulties and areas where
        more effort may be required in the data collection and design areas.


        2.  Preliminary engineering or basic engineering

        The primary objectives are normally:


        -  Perform pipeline design so that system concept is fixed. This will include:

           To verify the sizing of the pipeline;
           Determining the pipeline grade and wall thickness;
           Verifying  the  pipeline  against  design  and  code  requirements  for  installation,
           commissioning and operation;


        -  Prepare authority applications;


        -  Perform a material take off sufficient to order the linepipe (should the pipe fabrication be
           a long lead item, hence requiring early start-up)

        The level of  engineering is sometimes specified as being sufficient to detail the design for
        inclusion into an “Engineering, Procurement, Construction and Installation” (EPCI) tender.
        The EPCI contractor should then  be able to perform the detailed design with  the minimum
        number of variations as detailed in their bid.

        3.  Detail engineering


        The detailed engineering phase is, as the description suggests, the development of  the design
        to a point where the technical input for all procurement and construction tendering can be
        defined in sufficient detail.