Page 130 - Plant design and economics for chemical engineers
P. 130

106  PLANT DESIGN AND ECONOMICS FOR CHEMICAL ENGINEERS

         20. Review the benzene storage system shown on page 107 in which benzene enters tank
            T-l01  through a 4-in. line  L-l01  and is subsequently pumped out through pumps
            P-1OlA  and B at 35 atm into a 3-in. line L-102. The accompanying table shows that
            part of a HAZOP study of line G102 has been completed. Provide the missing
            information to complete the study.

         HAZOP for line G102
                                  Possible     Possible
         Guide word   pnwm        CBUSt?       consequence     Action  required
         More         Temperature     -        Pump  seal      Install a
                                                 failure,        feedback line
                                                 vapor lock
         Less         Temperature  Low  ambient     -          Steam tracing
                                    temperature
         More         Flow        Line  fracture  Spillage (possible
                                                 large explosion)
                                  Pump  seal   Spillage (possible
                                   failure       small explosion)
                                  Control fault                Consider bypass
         No           Flow            -        Shutdown        Low level alarm
                                               Shutdown        Automatic  startup
                                                                 of standby pump
         Reverse      Flow        Pump         Backpressure         -
                                    failure      on storage
                                                 vessel
         As well as   Impurities      -        Possible small  Priming line
                                                 detonation


         21. Produce a fault tree for the following system where the highest-order event is
            overpressure of the vessel. The possible causes of various failures should be sug-
            gested.













                                                     To  instrument
                                                      air system


         22. List all the areas in the sodium dodecylbenzene sulfonate process described in Chap.
            2 that could be potential danger areas with respect to the health and safety of
   125   126   127   128   129   130   131   132   133   134   135