PROBLEMS

                                          Determine the width of pillar, w p , required if the roadway next to one panel is to
                                        be outside the 10% zone of influence of the adjacent panel with respect to vertical
                                        stresses.

                                        4 An estimate of the dimensions of the flow and limit ellipsoids is required for use
                                        in preparing a preliminary sublevel caving layout. The trial height of gravity flow
                                        is to be h N = 16 m. Using Janelid and Kvapil’s approach with an eccentricity of
                                        ε = 0.973, and assuming the loosening factor for the material in the limit ellipsoid
                                        to be   = 1.080, calculate predicted values of the major and minor semi-axes and
                                        volumes of the flow and limit ellipsoids.
                                          What values of ring burden and slice width do these results indicate are required
                                        to minimise dilution and ore loss in sublevel caving operations?
                                        5 A 60 m high block of caved ore under a capping of waste is to be drawn using
                                        drawpoints spaced on 10 m centres. Field trials show that one drawpoint will pass the
                                        material originally contained within the ellipsoid

                                                              2
                                                            6x + 0.5(y − 1.4 V 1/3 2  2/3
                                                                               ) = V
                                        where x and y are measured horizontally and vertically from an origin on the centre-
                                        line at the top of the drawpoint, and V is the volume drawn. The caved ore has a unit
                                        weight of 25 kN m −3  and the loosening factor is   = 1.066.
                                        (a) Will the waste-ore contact be displaced by drawing 1000 tonnes of ore from one
                                            drawpoint?
                                        (b) How much ore can be drawn from one drawpoint before waste appears?