Page 39 - Shigley's Mechanical Engineering Design
P. 39

bud29281_ch01_002-030.qxd  11/11/2009  5:35 pm  Page 14 pinnacle s-171:Desktop Folder:Temp Work:Don't Delete (Jobs):MHDQ196/Budynas:







                 14    Mechanical Engineering Design
                  Figure 1–2                400
                                            380
                  Cost versus tolerance/
                                            360
                  machining process.        340
                  (From David G. Ullman, The  320
                  Mechanical Design Process,  300
                  3rd ed., McGraw-Hill, New  280          Material: steel
                                            260
                  York, 2003.)
                                            240
                                           Costs, %  220
                                            200
                                            180
                                            160
                                            140
                                            120
                                            100
                                             80
                                             60
                                             40
                                             20
                                              0.030  0.015   0.010   0.005   0.003   0.001  0.0005  0.00025
                                                  Nominal tolerances (inches)
                                               0.75   0.50   0.50   0.125   0.063   0.025   0.012   0.006
                                                    Nominal tolerance (mm)
                                                                     Semi-  Finish
                                                        Rough turn    finish  turn  Grind  Hone
                                                                      turn
                                                              Machining operations


                  Figure 1–3
                                            140
                  A breakeven point.
                                            120          Breakeven point

                                            100                       Automatic screw
                                                                        machine
                                           Cost, $  80

                                            60
                                                           Hand screw machine
                                            40
                                            20

                                             0
                                              0     20     40     60    80     100
                                                              Production


                                              As an example, consider a situation in which a certain part can be manufactured at
                                          the rate of 25 parts per hour on an automatic screw machine or 10 parts per hour on a
                                          hand screw machine. Let us suppose, too, that the setup time for the automatic is 3 h and
                                          that the labor cost for either machine is $20 per hour, including overhead. Figure 1–3 is
                                          a graph of cost versus production by the two methods. The breakeven point for this
                                          example corresponds to 50 parts. If the desired production is greater than 50 parts, the
                                          automatic machine should be used.
   34   35   36   37   38   39   40   41   42   43   44