Page 143 -
P. 143

7 - PROJECT COST MANAGEMENT






                   7.3.2.2 Reserve Analysis


                      A software project budget is based on the sum of estimates for all identified work activities plus an additional reserve
                   for work that will potentially emerge. During the project, reserved budget is either applied to meet contingencies or
                   preserved as surplus or profit. Ideally, as a project progresses and the risks and uncertainties are resolved, the amount
                   of reserve needed is reduced to zero by the end of a project. When charted over time, the amount of reserve needed
                   should resemble a cone (the “cone of uncertainty,” large at the beginning of the project and narrowing to zero by
                   the end of the project). The reserve may be divided between the amount that the project manager can use directly
                   (contingency reserve) and the management reserve, which will require authorization to be applied to the project.


                   7.3.2.3 Expert Judgment

                      See Section 7.3.2.3 of the PMBOK  Guide.
                                                    ®

                   7.3.2.4 Historical Relationships

                                                    ®
                      See Section 7.3.2.4 of the PMBOK  Guide.

                   7.3.2.5 Funding Limit Reconciliation

                      See Section 7.3.2.5 of the PMBOK  Guide.
                                                    ®

                   7.3.3 Determine Budget: Outputs


                      The outputs for determining budget in Section 7.3.1 of the  PMBOK   Guide (7.3.3.1 through 7.3.3.3) are
                                                                                   ®
                   applicable to determining the budget for software projects.


                   7.3.3.1 Cost Baseline

                      See Section 7.3.3.1 of the PMBOK  Guide.
                                                    ®

                   7.3.3.2 Project Funding Requirements

                      See Section 7.3.3.2 of the PMBOK  Guide.
                                                    ®

                   7.3.3.3 Project Documents Updates

                      See Section 7.3.3.3 of the PMBOK  Guide.
                                                    ®

                   7.4 Control Costs


                      The inputs, tools and techniques, and outputs for controlling costs in Section 7.4 of the PMBOK  Guide are
                                                                                                          ®
                   applicable to controlling costs of software projects, with the following clarifications.


          134      ©2013 Project Management Institute. Software Extension to the PMBOK  Guide Fifth Edition
                                                                   ®
   138   139   140   141   142   143   144   145   146   147   148