Page 287 - Standard Handbook Petroleum Natural Gas Engineering VOLUME2
P. 287

254    Reservoir Engineering


                   within  the  proved and  probable  limits,  (3) reserves in  formations that  have
                   favorable log  characteristics  but  questionable  productivity,  (4) reserves  in
                   untested fault segments adjacent to proved reservoirs where a reasonable doubt
                   exists as to whether such fault segment contains recoverable hydrocarbons, (5)
                   incremental reserves attributable to infill drilling that are subject to technical
                   or regulatory uncertainty, and (6) reserves from a planned improved recovery
                   program that is not in operation and that is in a field in which formation, fluid,
                   or reservoir characteristics are such that a reasonable doubt exists to its success.

                   Reserve Status Categories. These define  the  development and  producing
                   status of  wells  and/or  reservoirs. They may be applied to proved or unproved
                   (probable or possible) reserves.
                   Developed  Reserves.  These are expected to  be recovered from existing wells
                   (including reserves behind  pipe). Improved recovery reserves are  considered
                   developed only after the necessary equipment has been installed, or when the
                   costs to do so  are relatively minor. Developed reserves may  be subcategorized
                   as producing or nonproducing.

                    Producing  Reserves. These  are  expected  to be  recovered from  completion
                   intervals open at the time of  the estimate and producing to  market. Improved
                   recovery reserves are considered to be producing only after an improved recovery
                   project is in operation. Unproved (probable or possible) producing reserves are
                   in  addition  to  proved  prothing reserves,  such  as  (1) reserves  that  may
                   be recovered from portions of  the reservoir downdip from proved reserves or
                    (2) reserves that may  be recovered if  a higher recovery factor is realized than
                   was  used in  the estimate of  proved reserves.

                    Nonptvdwhg Reserves. These include shut-in and behind-pipe reserves.  Shut-in
                    reserves are  expected to  be  recovered from  completion intervals open  at  the
                    time of  the estimate, but which have not started producing, or were shut in for
                    market  conditions of  pipeline connection, or were  not  capable of  production
                    for mechanical reasons, and the time when sales will start is uncertain. Behind-
                    pipe reserves are expected to be recovered from zones behind casing in existing
                    wells,  which will  require additional completion work  or a future recompletion
                    prior to  the  start of production.
                    Undeveloped Reserves. These are expected to be recovered (1) from new wells
                    on undrilled acreage, (2) from deepening existing wells to a different reservoir,
                    or (3) where a  relatively large  expenditure is  required  to  (a) recomplete  an
                    existing well,  or (b) install production or transportation facilities for primary
                    or improved recovery projects. Undeveloped reserves usually will be distinguished
                    from developed reserves. The ownership status of  reserves may  change due to
                    the  expiration of  a  production  license or contract; when  relevant to  reserve
                    assignment, such changes should be identified for each reserve classification.

                                       Methods of  Estimating Reserves

                      Methods of  determining  reserves  progress from analogy, before  a well  is
                    drilled, to history after it is plugged and abandoned. The accuracy with which
                    reserves  can be  estimated progresses along the  same path  from  speculation
                    to history.
   282   283   284   285   286   287   288   289   290   291   292