Page 248 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 248

CHAPTER 13






                                                    CHP Construction





             Milton Meckler





                   he construction of a CHP plant may require undertaking considerable risks to all
                   parties involved. While most contractors are accustomed to dealing with risks,
             Tfirst time or less experienced CHP plant owner-operators are generally less
             informed about the risks they may encounter in the construction of a CHP project, and/
             or concerning the role they must be expected to play on the project construction team
             being assembled. This chapter is not intended to be a treatise on all the issues that con-
             tactors must normally address but is intended to address those issues that should be of
             principal concern in contractual relationships between contractor and their owner-
             developer clients when constructing CHP plants.
                Owner-operators and/or developers of CHP facilities must be made to understand
             from the outset that their role during the construction of a project is as integral to its
             success as that of the design engineer, architect, and contractor. In addition, owners
             should also understand that there are virtually no risks on a construction project that
             cannot be shifted among the contracting parties depending upon the type and terms of
             the owner-contractor agreement. For example, an owner-operator may contractually be
             required to assume the risks of unusually severe weather, unexpected subsurface
             conditions, strikes at the turbine or engine supplier’s manufacturing plant, changes
             in law or codes, increases in price, and delays to project completion associated with
             such risks.
                Accordingly, the CHP plant owner-operator and/or his prime general or mechanical
             construction contractor must consider not only whether there is sufficient financing to
             complete its construction, for example, but also be prepared to conduct a thorough risk
             management review and analysis of the project structure and its contracting terms,
             while incorporating the following principal goals, namely:

                  1.  Identify the most significant risks faced.
                  2.  Determine how such risks can either be mitigated or entirely eliminated.
                  3.  Conduct an assessment of the financial exposure should one or more of the
                    major risks identified under (1) result.
                The next section examines the steps that owner-operators and contractors of CHP
             projects can employ when undertaking a risk management review.

                                                                                   221
   243   244   245   246   247   248   249   250   251   252   253