Page 101 - The Engineering Guide to LEED-New Construction Sustainable Construction for Engineers
P. 101

82    Cha pte r  T w o


                    concrete and weathered asphalt pavements, and weathered and new concrete
                    pavement surfaces, respectively.
                  •  Open grid pavement systems. Variable O is defined as the area of the hardscape
                    which is covered in open grid pavement systems which are at least 50 percent
                    pervious with vegetation in the open cells.

                 The three pathways for reducing the heat island effect by keeping at least 50 percent
             of the non-roof hardscape as shaded, high SRI, or open grid cannot be superimposed on
             one another. In other words, an area that is both shaded and high SRI cannot be counted
             twice. There is some discretion with the shading value as it is an arithmetic mean of
             various areas determined by the angle of the sun, and if there is any question as to whether
             the appropriate areas are used, then these should be well documented. The easiest way to
             perform the calculations is to give modified definitions for R and O such that
             R       R   is the sum of the areas with high SRI excluding those areas that are shaded.
               mod    mod
             O         O   is the sum of the areas with open grid pavement systems that are not
               mod     mod
                     shaded or do not have high SRI values.
             By using these definitions, compliance with Option 1 can be determined if the following
             inequality is true:

                                        HS/2 ≤ (S + R   + O  )                   (2.7.1)
                                                   mod   mod

             Option 2  The calculations for Option 2 are simpler. First determine the total number of
             parking spaces (TP) for the project and then count the number of these total spaces that
             are under cover (CP) for which the top roofing material above them has an SRI of at least
             29 or is covered by solar panels or vegetation if under shading devices. Under cover
             includes underground, under the building, under a deck, and under shade structures
             such as canopies. If more than one-half of the parking spaces are under cover as so
             defined, then the credit is met. Note that this option only refers to the parking spaces
             themselves and does not mention anything about the parking aisles or other paved areas
             associated with these spaces. The equation for compliance with Option 2 is

                                             CP  ≥ TP/2                          (2.7.2)

             Special Circumstances and Exemplary Performance
             Submittals for both options should include the calculations for each option. In addition,
             for Option 1, the submittals should include site drawings showing all the non-roof
             hardscape areas with their heat island–related characteristics (shading, SRI, or open grid)
             and areas noted. The surface SRIs given may either be the actual for each paving material
             or as provided for similar mixes and ages on other projects. For Option 2, the submittals
             should include plans with the number of total parking spaces and parking spaces under
             cover with the appropriate roofed SRI or solar panel if under canopies. Option 2 is a great
             example of how design team members need to work together to obtain the LEED credits.
             The parking layout may sometimes be determined by others than the architectural roofing
             designer. Only together will this option be met.
                 Concrete is a common material used for many surface treatments and other
             structural components of the built facilities. Many concretes are made with a combination
   96   97   98   99   100   101   102   103   104   105   106