Page 200 - The Engineering Guide to LEED-New Construction Sustainable Construction for Engineers
P. 200

178   Cha pte r  F o u r



               Building Energy System   IPMVP Vol. III
               Types                  Option           Method Name
               Simple, easily isolated   Option B      Energy Conservation Measure (ECM)
               (LEED 2009 Option 2)                    Isolation
               Complex (LEED 2009     Option D         Whole Building Calibration Simulation
               Option 1)

             TABLE 4.5.1  Summary of IPMVP Approaches for EAc5


             addition to the development of an M&V Plan, there may be a substantial amount of metering
             which may be needed on various building systems to measure the energy usages and
             savings. Table 4.5.1 summarizes these two approaches.
                 It is important that the submittals include the IPMVP option chosen, a copy of the
             M&V Plan as written according to the requirements in IPMVP Volume III, appropriate
             models and calculations based on the data collected, and a narrative if there are any
             special circumstances or explanations of calculation methods. This submittal must
             cover at least a full year of postconstruction occupancy, with this minimum one year
             time period beginning after the building has reached a reasonable occupancy and use
             level. Therefore, it is not usually reasonable to schedule the submittal exactly one year
             from the certificate of occupancy (CofO), which may be issued by the local building
             official or building authority. Instead, the project team should estimate an occupancy
             schedule, keep track of the building occupancies, and have the one-year period begin
             after most of the uses are established. In the case where one group plans to be the sole
             occupant of the new building and move the entire workforce within a month of issuance
             of the CofO, then the one-year period may start relatively quickly after construction
             ends. In the case where an office building is constructed that has multiple occupants,
             there may be some floors or areas that may take a year or so after construction to find
             tenants, and the verification of this credit may take longer. If the expected energy
             savings are not being experienced, then a process for corrective action must also be
             submitted and implemented. There is also technical guidance for adapting this credit to
             projects with district energy systems on the USGBC Registered Project Tools page found
             at http://www.usgbc.org/projecttools.

             Special Circumstance and Exemplary Performance
             EAc5 has been given an EB notation by the USGBC. It is also designated as a credit
             that needs a construction phase submittal, as much of the activity is during or
             postconstruction. There is no EP point available for this credit.


        4.6  EA Credit 6: Green Power
             The intent of EAc6 is to encourage the use of power from a power grid that has been
             made from renewable energy sources. Projects were awarded one point for this credit
             in LEED 2.2 and will be awarded two points in LEED 2009.
             USGBC Rating System
             LEED-NC 2.2 lists the Intent, Requirements, and Potential Technologies and Strategies
             for EAc2 as follows, with additional verbiage from LEED 2009 to number the options:
   195   196   197   198   199   200   201   202   203   204   205