Page 134 - The Green Building Bottom Line The Real Cost of Sustainable Building
P. 134

GREEN IS THE COLOR OF MONEY  113



                       discover they were learning with us and knew little more than we did. We incurred pre-
                       mium pricing for materials and technologies either out of our own ignorance or because
                       prices had yet to become competitive. We faced up-charges in architectural fees as a result
                       of re-designing projects in the midst of construction because we were changing our envi-
                       ronmental performance objectives as we were building. And, not surprisingly, we suf-
                       fered from delayed receipt of rent because our projects were taking longer to complete.
                         We estimate that our first LEED project, the Whitaker Building, probably saw a 15
                       percent cost overrun as a result of our learning curve (approximately $150,000). It did
                       not help that our first project involved renovation of a 19th century building on the
                       National Historic Register, challenging us to meld historic constraints to stringent con-
                       temporary energy standards. Our learning curve on that development in terms of time
                       and process was a significant part of the cost premium.
                         We estimate that our second project, Abercorn Common, also entailed a premium as
                       a result of our learning the LEED program. Much of this premium is factored into our
                       discussion of this project in Chapter 5. However, it’s worth pointing out there that a
                       significant portion of our premium came in the form of longer time delivery to market
                       and with that delay, deferral of rental income (approximately $417,000). It’s almost
                       impossible to calculate how much of that delay was owing to making this building
                       green and how much to other factors that many development projects face (threatened
                       litigation from a neighboring retailer, changes in design, uncertainty in the retail market
                       post-9/11, etc.). Since those first two projects (Whitaker and Abercorn), the premium
                       we calculate paying for green development has declined to the point where we feel it
                       is largely negligible. An overview of the cost of our learning curve on our first four
                       LEED projects, amounting to roughly $1.5 million, can be seen in Table 4.2.




                 TABLE 4.2  COST OF LEARNING CURVE ON EARLY LEED PROJECTS

                                                                     LEED
                 PROJECT    PROJECT    LEED    PREMIUM   PROJECT   PREMIUM    LOST
                 NAME         TYPE   CATEGORY     (%)     COST        ($)    INCOME   TOTALS
                 Whitaker    Office/    New      15.00% $ 1,211,479 $ 150,000
                             Retail  Construction
                 Abercorn:   Retail  Core & Shell  4.60% $18,293,000 $ 840,000 $416,667
                 In-line
                 McDonald’s  Retail  Core & Shell  4.60% $ 1,410,000 $  50,000
                 Building 600  Retail  Core & Shell  4.60% $ 1,788,000 $  57,000

                 Learning                                         $1,097,000 $416,667 $1,513,667
                 Curve Totals
                 Cost of LEED                                                       $   48,850
                 Education
                 Total Cost                                                         $1,562,517
   129   130   131   132   133   134   135   136   137   138   139