Page 37 - Thermal Hydraulics Aspects of Liquid Metal Cooled Nuclear Reactors
P. 37

12                    Thermal Hydraulics Aspects of Liquid Metal Cooled Nuclear Reactors

         the in-pile test sections and the beam tube, fuel handling is done from underneath the
         core. Two in-vessel fuel-handling machines fulfill this function. The primary, second-
         ary, and tertiary cooling systems have been designed to evacuate a maximum core
         power of 110MW(th). The primary cooling system consists of two pumps and four
         primary heat exchangers. The secondary cooling system is a water-cooling system,
         providing pressurized water to the primary heat exchangers. The tertiary cooling
         system is an air-cooling system.

         1.5.3.3 Description of the safety concept

         In case of loss of the primary flow, the beam must be shut off in subcritical case and the
         safety rods inserted in critical mode. The primary, secondary, and tertiary cooling sys-
         tems have been designed to remove the decay heat using natural convection. Ultimate
         decay heat removal is achieved by the reactor vessel cooling system, also by natural
         convection. In the unlikely event of a reactor vessel breach, the reactor pit will fulfill
         the function of secondary containment to keep the lead-bismuth in place.


         1.5.3.4 Deployment status and planned schedule
         The implementation of MYRRHA follows a phased approach. In phase 1 (2016–24), a
         100MeV particle accelerator will be constructed together with stations for the produc-
         tion of radioisotopes and material research. Hence, in 2024, a first R&D facility will
         become available. In parallel, the preconstruction engineering and design of the reac-
         tor will continue and conclude. The prelicensing phase will conclude, and the licens-
         ing phase will start.
            In phase 2 (2025–30), the 600MeV particle accelerator and the reactor will be
         developed and constructed. The end of the construction phase is foreseen by 2030
         and end of commissioning by 2033.


         1.5.4 SEALER (Fig. 1.5)


          Full name:                  Swedish Advanced Lead-cooled Reactor
          Designer:                   LeadCold Reactors
          Reactor type:               Pool
          Electric capacity:          3MW(e)
          Thermal capacity:           8MW(th)
          Coolant:                    Lead
          System pressure:            0.1MPa
          System temperature:         390°C/430°C (core inlet/outlet)
          No. of safety trains:       2
          Emergency safety systems:   Passive
          Residual heat removal systems:  Passive
          Design status:              Conceptual design
          New/distinguishing features:  Full decay heat removal by radiation through vessel
                                      High-density shutdown rod absorber
                                      No fuel reload during 30 years of operational life
   32   33   34   35   36   37   38   39   40   41   42