Page 49 - Water and Wastewater Engineering Design Principles and Practice
P. 49

1-20   WATER AND WASTEWATER ENGINEERING

                            In general this is the responsibility of the client because, as noted in the second canon of the
                            Code of Ethics, it falls outside of the area of competence of the engineer. The client hires some
                            combination of qualified and experienced people to do this work. A team may consist of a
                            registered land surveyor, attorney, and government official familiar with the community. The
                            engineer’s role is to provide guidance with respect to the requirements of the design. If neces-
                            sary, the engineer may also be called on to perform environmental site investigations to ensure
                            the site(s) are free of hazardous materials. Of course, this effort should be included in the scope
                            of work.
                                 Options on the land to be purchased and freely given easements provide a means of expe-
                            diting the construction process without making an unalterable commitment before the detailed
                            design and bid estimate are completed. These are essential for the final design, and they also
                            provide cost information for the estimate of total funding of the project.
                                Once property bids have been accepted, final land acquisition can begin. For those not will-
                            ing to give or sell land for the treatment facility or easements for the water main or sewer, con-
                            demnation proceedings may be instituted. This may cause a substantial delay in the start and
                            completion of the project and should be anticipated in the bid documents.


                              Bid Letting
                             Bid documents may be disseminated in a variety of ways. Many municipalities have developed a
                            program of prequalification of bidders and an invitation to bid is sent only to qualified bidders.
                                At some reasonable time interval, after the bid package is disseminated to interested contrac-
                            tors, a prebid meeting is held to answer questions and clarify requirements of the bidders. This
                            meeting may be either mandatory or optional. The engineer and the owner’s contracting officer
                            are present at this meeting. Substantive questions are answered, in writing, to all participants by
                            issuing a bid document addendum.
                                  When the bids are received, the engineer assists the owner in determining the lowest qualified
                            bidder. The bid must be responsive in that it meets the specifications without unacceptable substi-
                            tutions and agrees to meet the stated completion date. In addition, the bidder must have appropri-
                            ate licenses, bonding, and insurance. A qualified bidder must also be free of outstanding claims
                            and liens from previous work. Appropriately licensed personnel and people qualified to supervise
                            the work should also be included in consideration of whether or not the bidder is qualified.
                                 This is a critical decision point in the project. First, the decision to proceed must be made.
                            Second, the decision(s) on the awardee(s) must be made. As at all the previous decision points,
                            the client must be given appropriate information to make informed decisions.


                              Construction
                             Before construction begins, a preconstruction meeting is held. All parties (engineer, owner, con-
                            tractor) meet to review the contractor’s schedule, special provisions, sequence of construction,
                            payment process, and progress meetings schedule.
                                During the construction process the engineer determines if the work is proceeding in accor-
                            dance with the contract documents. For large projects, a full-time resident project representa-
                            tive  (RPR) is on site. For small projects, the engineer provides periodic inspection and special
                            inspection at critical construction milestones. Thus, for small projects it is imperative that critical
   44   45   46   47   48   49   50   51   52   53   54