Page 231 - Well Control for Completions and Interventions
P. 231

Well Barriers                                                225


                 Note: Some coil tubing operations use reverse circulation to clean out the well-
              bore. This means no check valves are included in the BHA. In these circumstances,
              the primary internal barrier is provided by maintaining overbalance on the forma-
              tion to prevent hydrocarbons from entering the reel.





                   6.8 HYDRAULIC WORKOVER (SNUBBING) UNIT: LIVE
                   WELL OPERATIONS
                   6.8.1 External pressure control

              Primary Barrier.
             •  Stripper rubbers or annular preventer.
             •  If rigged up on top of a Christmas tree, the tree gate valves provide
                the primary barrier when rigging up and when lubricating tools in
                and out of the riser.
             •  If no Christmas tree is installed, tools are lubricated in and out of the
                well above closed BOP blind rams.
              Secondary Barriers (pipe in the well).
             •  2 x BOP pipe rams.
              Tertiary Barrier.
             •  BOP shear and blind rams or a shear seal ram.



              6.8.2 Internal pressure control
              Primary Barrier.
             •  Check valves (nonreturn valves) in the BHA.
              Secondary Barrier.
             •  A full opening stab-in safety valve (Kelly Cock).
              Tertiary Barrier.
             •  Shear ram and blind ram or shear/seal ram on the BOP.
             •  Facility to kill or plug the well: pumps, kill weight fluid, LCM,
                cement, etc.





                   6.9 WELL BARRIER SCHEMATICS

                   Well schematics have been used by the oil industry for many years
              to provide a simple overview of the well architecture, and list critical