Page 383 - Moving the Earth_ The Workbook of Excavation
P. 383

ROADWAYS

                                                                                           ROADWAYS    8.45

                                  inside wheels of the scraper sink more deeply. If it becomes too steep, it is readily reduced by filling
                                  toward the center.
                                    If the job is shut down during any period when rain is expected, it may be wise to build the fill
                                  up to a crown in order to allow it to drain. This involves resloping the edges on resumption of work,
                                  and, if the work is done under exact compaction specifications, may cause confusion in the treat-
                                  ment of the tapered layers required.
                                    Another treatment is to preserve the trough but so grade it that all water will flow to selected
                                  low spots. Here ditches are dug through the raised edges, and troughs of metal or wood placed to
                                  lead the water down the slope. This is readily done in hilly country, where most of the road is on
                                  definite gradients, but not in level country.
                                    Such drain ditches may be made wide and gentle, so that they can be dug, backfilled, and com-
                                  pacted by machinery, or may be hand-dug, refilled, and tamped.
                                    If the trough shape is left without precautions, a center gully may be scoured by a heavy rain,
                                  a pond formed in low spots, and damage done to edges by overtopping and concentrated runoff.
                                    Scraper distance from the edge is determined by depth of spread and slope. If a slope is 1 on 2, spreads
                                  are 6 inches deep, and compaction is one-third, each pass will be 8 inches inside the previous one.
                                    If the edge is not firm enough to support scrapers at the proper distance to dump loads, they
                                  should be spread farther back and dirt cast out to the edge by a grader or angling dozer.
                                    Additional slope stakes should be set as a high fill is built up to maintain the correct width.


                      DRAINAGE


                                  Drainage is an important factor in the construction of most roadways. Groundwater must be kept
                                  far enough below the surface so as not to damage it, or weaken the subgrade directly or by sup-
                                  plying capillary water. Water falling on the surface of the road must be conducted off it, and
                                  runoff or streams crossing the road must be provided for.

                                  Raising the Grade.  In swamps and lowlands, the only practical method of getting the road well
                                  above groundwater is to build a high fill. If the base course can be made entirely of rock, it will
                                  break any contact between the water and the balance of the fill. Clean gravel or coarse sand may
                                  serve the same purpose.
                                    Proper quality of fill can reduce the required height substantially. However, it is often more
                                  economical to make a higher fill of inferior material obtained from roadside ditches, as in Fig.
                                  8.33(A), and it is often possible to lower the water level by the same operation. Draglines or exca-
                                  vators are generally used, but dipper dredges may be preferred when much of the land is under
                                  water, or it is intersected by numerous channels.
                                    Either machine may work along the ditch lines, piling spoil toward the center, as in (B). The
                                  dragline will work away from the cut, as shown, but the dredge will float in it.
                                    If a dragline has a sufficiently long boom, it can travel on the road centerline, and dig both
                                  ditches and pile the spoil in one pass, as in (D).
                                    Road fill may also be obtained by ditching in dry flatlands where the road is to be raised above
                                  floods or snowdrifts. In such circumstances elevating graders may be used as shown in Fig. 8.34,
                                  or dozers or scrapers.

                                  Tiling.  In sloping land, it is usually more economical to lower the water table by drainage. The
                                  standard method, Fig. 8.35, is to put shallow ditches to carry surface water through cuts (A), and,
                                  if necessary, to place porous tile or other drains (B) 2 to 3 feet deeper in loam soils. Silt or clay
                                  deposits may require a drain depth of as much as 7 feet, but in such a case, better results may be
                                  obtained by a normal drain depth and by the use of a layer of pervious material under the road.
                                    The design of subsurface drains must be carefully adapted to the requirements of the particu-
                                  lar job. The ground may drain naturally so that no work is necessary. There may be a saturated
                                  condition that could be relieved by providing a drain through an impervious barrier (C), or by cutting
   378   379   380   381   382   383   384   385   386   387   388