Page 386 - Moving the Earth_ The Workbook of Excavation
P. 386

ROADWAYS

                   8.48   THE WORK

                               Basic Factors.  Basic factors to be considered in figuring grading for a road may include
                                1. Clearing costs
                                2. Topsoil stripping, storage, reclamation, spreading, and planting
                                3. Amount and type of soil excavation in cuts or borrow pits
                                4. Amount and type of rock excavation
                                5. Availability of suitable borrow and cost of purchase
                                6. Haul road construction and maintenance, and length of hauls
                                7. Quality of fill required, and processing required of material from cuts and pits
                                8. Fill compaction, shrinkage, and disposal of surplus
                                9. Slope finishing and protection
                               10. Groundwater conditions and drainage requirements
                               11. Structures such as bridges, culverts, and retaining walls
                               12. Possession or availability of proper machinery, with necessary parts and supplies; extra costs
                                   of using second-choice or beat-up equipment
                               13. Availability of construction supplies such as pipe, forms, etc.
                               14. Labor supply
                               15. Weather—rain, snow, ice, dust, frozen ground, frozen equipment, mud
                               16. Time of completion of related structures such as bridges, being built under separate contract
                                 In roadway work, the amount, kind, and location of cut, borrow, and fill, and the length of haul,
                               may be specified. Haul may be described as normal or free, up to a certain distance, which may be
                               300 to 1,000 feet, and longer hauls called overhaul. Excavation may be described as unclassified,
                               or divided into rock yards and dirt yards.
                                 In less formal jobs, these factors may be indicated only approximately, or may be figured by
                               the contractor from grade or route plans.

                               Casual Estimating.  Where cuts and fills are shallow, and side slopes lacking or moderate, grad-
                               ing can often be estimated fairly accurately by inspection of centerline stakes. The exact yardage
                               is sometimes not of primary importance, as stripping topsoil and working over a piece of ground
                               represent an amount of machine time that may be only moderately increased by the cuts and fills.
                                 Several errors must be watched for, however. Cuts and fills on the stakes may be figured from
                               the top of the stake, from ground level, or from a line on the stake. The grade indicated may be
                               subgrade, in which case it is taken at face value, or finish grade when the depth of base courses
                               and of surfacing must be added to the cuts and subtracted from the fills. The width to be figured
                               on is not only the road and shoulders, but also gutters and slopes. The depth of topsoil to be
                               stripped is subtracted from the cuts, added to the fills, and considered separately as an important
                               cost factor.
                                 When cuts or fills are deep, side slopes exist, topsoil need not be stripped, or when the job is large,
                               yardages should be carefully calculated. If this is not done on the plans, the contractor can do it.

                   YARDAGE CALCULATION


                               Center Profile.  The minimum staking for a road is the centerline. When this is done, a profile
                               is taken, showing the elevation of the ground at each stake. These elevations are plotted on cross-
                               section paper, usually with the vertical scale 10 times the horizontal, and the points connected by
                               a line. A profile for the road is then sketched in according to the standards of grade and vertical
                               curve required, or from some previously formed plan. This line should represent the subgrade
                               before the addition of any imported material.
   381   382   383   384   385   386   387   388   389   390   391