Page 532 - Moving the Earth_ The Workbook of Excavation
P. 532

PIT OPERATION


                   10.38  THE WORK
























                   FIGURE 10.26  Perched water table.


                                 Pit pumping follows the practices described in Chaps. 5, 6, and 21. It usually consists of
                               removing open water standing against or over the deposit being dug. A small sump is generally
                               made by digging part of the hole more deeply and placing the suction hose in that.
                                 Success in pumping depends on the relation between the volume of water in the hole and the rate
                               of inflow, and the capacity of the pump or pumps. Costs per gallon are usually smaller, and work
                               can be started or resumed more promptly if the pumps are oversize and can handle many times the
                               volume of inflow, so that a large part of their capacity can be used to lower the open water.
                                 Extensive gravel layers may contain billions of gallons of water over areas of many square
                               miles, which will drain into the sump. If no rain falls, the rate of flow gradually declines as the
                               continued drainage flattens the hydraulic gradient, but this situation requires handling so much
                               water that expenses are usually too high.
                                 If the gravel is of limited depth, much of the inflow might be sealed by cement grout forced
                               down into the gravel at pit boundaries, or where flow channels are suspected. Pumping should be
                               stopped before and during the grouting.
                                 In gravel formations of limited size, and in tight materials such as clay and peat, the original
                               rate of inflow usually declines rapidly, and the underground reservoir may be exhausted so that
                               inflow will stop until it rains.
                                 Each time a wet pit is enlarged by working, the pumping job of reopening it becomes greater
                               because of the increased pond volume.
                                 Pumping should be done in dry seasons when the water is lowest and interruption from rain
                               least likely. In general, it is better practice to pump out, dig a large volume as quickly as possible,
                               and allow to refill than to maintain pumping and a slow digging rate over a long period. This is
                               particularly true in the porous, quick-filling formations.
                                 Both surface and underground water are sometimes removed by pumping out of deep wells
                               drilled in the pit floor or near its boundaries. This method is particularly suited to plant supply.


                   PIT PLANNING

                               Pits may be opened casually by digging in a roadside bank, or large sums may be spent on inves-
                               tigations, plans, road building, and site preparation, before work is started. Most of them start with
                               small equipment and output and increase in scale if they prosper.
   527   528   529   530   531   532   533   534   535   536   537