Page 537 - Moving the Earth_ The Workbook of Excavation
P. 537

PIT OPERATION


                                                                                        PIT OPERATION  10.43

                                    Conveyor belts and cable excavators and, to a smaller extent, scrapers are largely confined to
                                  work inside pits. Trucks are equally adapted to inside hauling and outside delivery. On very long
                                  hauls, heavy materials are more economically moved by standard gauge rail.
                                    Conveyor belts may be considered either hauling units or part of the plant itself. They move
                                  and elevate material with minimum effort, but are usually difficult to set up and locate. They may
                                  be used instead of haul roads and trucks for delivery of a heavy volume of material to a single
                                  point many miles away.
                                    Trucks are excellent flexible, general-purpose units. They are available in a wide range of stan-
                                  dard sizes and can be adapted to different-size loaders or production schedules by varying the
                                  number on the run.
                                    Scrapers, to operate as such, need ground they can dig and hoppers which they can drive
                                  across, or storage areas giving them room to maneuver. Banks which they cannot dig can be
                                  loaded into them. However, scrapers are more costly and are usually slower than dump trucks of
                                  the same size, so it is not good practice to use them steadily under shovels.
                                    A scraper can dump beside a sunken hopper which is kept filled by a dozer.
                                    Truck hauls may be kept short by adding conveyor belts to the plant. The new belt will dump
                                  on the receiving end of the previous belt. Such installations may be quite long and are justified
                                  whenever considerable yardage will be handled.
                                    Hoppers which are built so that the truck can drive straight across, instead of backing to dump,
                                  are more expensive to construct but will allow a faster truck cycle. Such hoppers can also be used
                                  for scrapers.



                      SELECTIVE DIGGING

                                  Selective digging may be done to separate, at the face, two or more materials of value and to
                                  remove them; to remove one or more formations, leaving unwanted material; or to dig two or
                                  more materials so as to combine them.
                                    Any or all of the spoil from these operations may be hauled away or sidecast.
                                  Layers.  If the different formations are in vertical sheets, as in Fig. 10.28(A), any machine which
                                  is accurate enough to work the narrowest vein can be used. If they lie horizontally, as in (B), any
                                  excavator can move them if they can be cut as separate banks. If they are horizontal, and two or
                                  more must be removed at once, the excavator should be able to work from the top down. If divi-
                                  sions run in several directions, and separation must be exact, a Gradall excavator, with assistance
                                  from hand labor, could be used.
                                    When horizontal layers are separated by a dragline, as in (C), it should have a boom at least
                                  twice as long as the bank is high. The boom angle should be low and the dump cable short to make
                                  possible picking up the bucket at a distance.
                                    A clamshell can do the same work with a shorter boom as no allowance need be made for space
                                  to drag the load.
                                    Inclined strata fall into any of the above classes. In general, it is bad practice to remove enough
                                  of any layer to leave the one above it overhanging.
                                    Selective digging is quite commonly required in stripping overburden, and in gravel and clay
                                  pits. The operator may have the responsibility of choosing the section of bank most suitable to
                                  plant or customer requirements, and supplying deficiencies by mixing different sections or layers.

                                  Mixing.  A good way to mix at the bank is to build a stockpile by dumping several materials on
                                  one spot. A conical pile will be built, with each bucket load separating and sliding down the sides.
                                  A succession of very thin layers will be made which, upon redigging to load, should mix together
                                  quite smoothly.
                                    Such a pile will tend to concentrate round or coarse pieces at the bottom, but these will be
                                  remixed in handling by a machine working from the bottom.
   532   533   534   535   536   537   538   539   540   541   542