Page 17 -
P. 17

1.4                        CHAPTER ONE

           Major design decisions today are no longer made unilaterally by the project team. In-
         stead,  a  consensus is reached  after  participation by members of the  design team and by
        individuals outside  the  team,  including owners,  operators,  regulatory  agencies,  and the
         general public.



         Project Delivery
         The traditional procedure for construction of a new water treatment plant was for the en-
         gineering design and specifications to be prepared by an engineering finn or the owner's
         in-house staff. Bids were then taken, and the contract was  awarded to the lowest respon-
         sible bidder.  The  design team usually monitored the  construction to  see  that  the  design
         intent was carried out, and after construction was completed, the facilities were operated
         by the owner.
           Today, a number of changes and variations to this traditional approach are being con-
         sidered or implemented. Two of the principal alternatives are

         •  Design-build  approaches,  in  which  one  entity  is  responsible  for  both  design  and
          construction
         •  Privatization approaches,  in which  the facility is owned  by a  private entity providing
          treatment service for the water utility
           In addition, a global marketplace for water treatment engineering has developed. Ideas
         and practices  are  being exchanged  among countries all over the  world.  In North  Amer-
         ica,  there  is increasing consideration of European treatment practices,  technologies, and
         firms.



         DEVELOPMENT  OF WATER  TREATMENT
         DESIGN PROJECTS

         A  water treatment design project passes  through many steps between the  time when the
         need for a project is identified and the time that the completed project is placed into ser-
         vice.  The  period  before  construction commences  can  generally be  divided  into the  fol-
         lowing phases:
         1.  Master planning.  Treatment needs and feasible options for attaining those needs are
           established in a report.  In subsequent phases,  this report may be periodically updated
           to adjust to both system and regulatory changes.
         2.  Process train selection.  Viable treatment options are  subjected to  bench, pilot, and
           full-scale treatment investigations. This testing program provides background data suf-
           ficient in detail to enable decisions on selecting the more advantageous options for po-
           tential implementation. These tests provide design criteria for major plant process units.
         3.  Preliminary design.  In this  "fine-tuning" procedure,  feasible alternatives for princi-
           pal features of design, such as location, treatment process arrangement, type of equip-
           ment, and type and size of building enclosures, are evaluated. In this phase,  prelimi-
           nary  designs  are  prepared  in  sufficient detail  to  permit  development  of  meaningful
           project cost estimates.  These estimates  help in evaluating and selecting options to be
           incorporated into the final design and allow the owner to prepare the required project
           financial planning.
   12   13   14   15   16   17   18   19   20   21   22