5 - PROJECT SCOPE MANAGEMENT






                   5.2.1 collect requirements: Inputs



                   5.2.1.1 Scope Management Plan

                      Described in Section 5.1.3.1. The scope management plan provides clarity as to how project teams will determine
                   which type of requirements need to be collected for the project.


                   5.2.1.2 requirements Management Plan                                                                   5

                      Described in Section 5.1.3.2. The requirements management plan provides the processes that will be used
                   throughout the Collect Requirements process to define and document the stakeholder needs.


                   5.2.1.3 Stakeholder Management Plan

                      Described in Section 13.2.3.1.  The stakeholder management plan is used to understand stakeholder
                   communication requirements and the level of stakeholder engagement in order to assess and adapt to the level of
                   stakeholder participation in requirements activities.


                   5.2.1.4 Project charter

                      Described in Section 4.1.3.1. The project charter is used to provide the high-level description of the product,
                   service, or result of the project so that detailed requirements can be developed.


                   5.2.1.5 Stakeholder register


                      Described in Section 13.1.3.1. The stakeholder register is used to identify stakeholders who can provide
                   information on the requirements. The stakeholder register also captures major requirements and main expectations
                   stakeholders may have for the project.



























                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   113


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   134   135   136   137   138   139   140   141   142   143   144