11 - PROJECT RISK MANAGEMENT
11.6.3 control risks: outputs
11.6.3.1 Work Performance Information
Work performance information, as a Control Risks output, provides a mechanism to communicate and support
project decision making.
11.6.3.2 change requests
Implementing contingency plans or workarounds sometimes results in a change request. Change requests are
prepared and submitted to the Perform Integrated Change Control process (Section 4.5). Change requests can
include recommended corrective and preventive actions as well.
• recommended corrective actions. These are activities that realign the performance of the project
work with the project management plan. They include contingency plans and workarounds. The latter
are responses that were not initially planned, but are required to deal with emerging risks that were
previously unidentified or accepted passively. 11
• recommended preventive actions. These are activities that ensure that future performance of the
project work is aligned with the project management plan.
11.6.3.3 Project Management Plan updates
If the approved change requests have an effect on the risk management processes, the corresponding component
documents of the project management plan are revised and reissued to reflect the approved changes. The elements
of the project management plan that may be updated are the same as those in the Plan Risk Responses process.
®
©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition 353